Tesla Terafactory Texas Update

Welcome back guys, it’s Randy! Hopefully everyone had a great Thanksgiving and was able to spend some quality time with family and friends. Today’s footage shows work resuming after the break as it was good to see most of the workers be able to take a break as well. Jeff covered the site during the holiday and there was only a very small presence there each day. The big news that was posted yesterday by Eva Fox at Tesmanian, which I’ll link in the description, is that the 5 areas for the factory that Tesla requested a review on previously were all updated to the “Review Complete'' status! Hopefully this will mean that we’ll start to see these areas beginning production soon and we’ll start to see vehicles being produced within the coming weeks!
Here are today’s key takeaways:
- The north end shows a new concrete walkway leading to a pair of human-sized steel doors has been poured.
- The GigaPress area shows concrete poured where we last saw forms being constructed and we can also see additional conduit being laid in trenches on both sides of this slab, in addition the the area around it being prepped to be formed for concrete in the coming days. On the east side of this building, we see more concrete pouring in progress and can see how they are working their way to the north, so hopefully we’ll see all of this as finished concrete by the end of the week.
- The East detention pond looks to be mostly completed as we can see the sod and vegetation installed and they have applied hydro mulch to the banks of the pond except for the west side, which will most likely be finished on Tuesday. The overflow drainage channel in this area also looks finished as it shows hydro mulch and erosion blankets now in place along the banks of the entire channel.
- The Stamping area shows more heavy equipment ready to be moved into the building. We can also see that all of the shipping crates with the blue and silver tops have been moved directly next to the building indicating that whatever is in them is also about to be assembled and moved into the building.
- A wide view of the south end shows the progress remaining covering the southern gap roof, along with some other details we’ll cover, starting with 2 large heavy pieces of equipment being delivered that we can see atop the upper level access platform. We can also see that work has started to install the wall panels along this south facing side of the building.
- The south detention pond's south wall overflow system shows the box they formed has had the outer wall concrete poured and it looks like work is taking place to cover the top. The largest area of the pond is now having the final layer of topsoil applied, so it’s likely we’ll see vegetation brought in here soon like we did at the pond on the east side of the factory. The wall area shows efforts underway to enclose the pipe inlet box area and that final grading of the channel leading to the pipes has been completed. We see geotextile fabric in place before the next phase to finish this section begins. The drainage weir splitter box shows major progress in covering the box, which will be completed by the end of the day on Monday with the metal decking. We could see concrete being poured some time on Tuesday.
- The west side of the factory shows paving for the additional lots taking place in the large section of the berm that was cut out a couple of weeks ago and they are steadily working their way north.
- The BCP building window installation is complete, with the exception of the windows right at the corners of both the top and bottom rows.
- Lastly, we get a quick look over the far east side of the property and circle back to see the drainage pipe finally being updated and extended in the east parking lot area. We can see just how far they’ve extended it and it looks like it’ll stop where we see it right here.
--------------------------------------------
Support Me On Patreon or PayPal
/ terafactorytexas
paypal.me/davismediasolutions
--------------------------------------------
Date Filmed: 11-29-21
Time of Day: Late Afternoon - 3:30pm
--------------------------------------------
Social Media
Twitter: / terafactorytx
--------------------------------------------
Additional Terafactory Texas Footage Channels
@JeffRoberts - / peterdog15
@JoeTegtmeyer - / joetegtmeyer
@TxTerafactory - / texasterafactory
--------------------------------------------
Giga Berlin Footage
The Wolfpack Berlin: / thewolfpackberlin
--------------------------------------------
Music
Turn Up Burn Up - Diamond Ortiz
Drifting at 432Hz - Unicorn Heads
--------------------------------------------
Additional Info
www.tesmanian.com/blogs/tesma...

Пікірлер: 86

  • @guyhazelzet6240
    @guyhazelzet62402 жыл бұрын

    Thanks Randy, nice to have you back. You give a different perspective than Jeff. He flies the same pattern but you explore important areas and other areas of interest that day. I always enjoy that.

  • @beaumershon3066

    @beaumershon3066

    2 жыл бұрын

    I skip through about half of Jeff's videos everyday.

  • @grateful7839
    @grateful78392 жыл бұрын

    Yay TEXLA Randy

  • @ChrisHplusland
    @ChrisHplusland2 жыл бұрын

    8:50 Now I see they just need a couple elbows here and everything can be back filled. Thanks

  • @amyferguson6573
    @amyferguson65732 жыл бұрын

    Randy, I really appreciate how slow and thorough your videos are. I really like how you give the viewer a chance to see what’s being done. I rather see that than the whole entire area where things are mostly being stored. I like seeing those areas also but it’s nice to see what the workers are doing for a little bit before moving on. So my thanks.

  • @TerafactoryTexas

    @TerafactoryTexas

    2 жыл бұрын

    You are very welcome!

  • @jbbuzzable
    @jbbuzzable2 жыл бұрын

    It is mind boggling how much skill and effort has been dedicated to the management of water on this project. Great job!

  • @davidanalyst671

    @davidanalyst671

    2 жыл бұрын

    not really. its austin and it rains like a MF'er in may. Everywhere in austin has drainage plans for everything because it rains so much.

  • @jbbuzzable

    @jbbuzzable

    2 жыл бұрын

    @@davidanalyst671 What improvements would you suggest?

  • @DavidJohnson-tv2nn

    @DavidJohnson-tv2nn

    2 жыл бұрын

    Excellent design! Execution of plan leaves much room for improvement. Two recent examples.... 1) Trying to lay geomembrane liner in south pond before a rain event with no temporary containment pond in place, resulted in destruction of said liner. They actually filled in an area that they had to dig out later for the temporary pond! 2) East pond -- They ripped open one of the stormwater pipes before the long Thanksgiving weekend. Resulting in the biofiltration basin receiving some silting.

  • @eltonray2934

    @eltonray2934

    2 жыл бұрын

    The city of Austin dictates most of the control of water runoff. They made suggestions, the general contractor drew up plans to include their requirements and I am sure that Tesla had to approve them. The result is that there is some deviation from the civil plans, but the function remains the same with the approval of the city engineers. Every detail is included in the civil plans including temporary dirt storage, dust control by the water trucks and almost every other aspect of construction. They probably have city inspectors living on site at Tesla's expense.

  • @jbbuzzable

    @jbbuzzable

    2 жыл бұрын

    @@eltonray2934 You still have not stated what your perceived problem is. Edit: Like how does this relate to the Tesla factory?

  • @islammohamed1441
    @islammohamed14412 жыл бұрын

    great backing track. nice fluid flybys. You and WuWa are artists with a drone Thanks for the sweet update Randy!

  • @philnichols5611
    @philnichols56112 жыл бұрын

    Very thorough job ! You and Tegtmeyer do a very complete review. Thanks

  • @ismailnyeyusof3520

    @ismailnyeyusof3520

    2 жыл бұрын

    I completely agree, Randy and Joe really get into the details and I appreciate that.

  • @MrFoxRobert
    @MrFoxRobert2 жыл бұрын

    Thank you!

  • @dahveed284
    @dahveed2842 жыл бұрын

    I was in Georgetown for Thanksgiving. So Friday morning I drove out there to see the building. I was there at about 10:00am and they were working hard that day. It is huge. My brother in law insists there are people already in the office section of the building working. Like its finished out inside and Tesla people are already working there. I'm not sure.

  • @MysticRiverRC
    @MysticRiverRC2 жыл бұрын

    Once again, beautiful work Randy. Thank you so much for your detailed flyovers.

  • @ralfrudiracer
    @ralfrudiracer2 жыл бұрын

    Sehr schönes Video, ruhig, genug Zeit zum Schauen und doch systematisch!

  • @dan_w3st
    @dan_w3st2 жыл бұрын

    Great video, thanks Randy! Enjoyed the music.

  • @andreandre1051
    @andreandre10512 жыл бұрын

    Merci👍👍👍

  • @acmefixer1
    @acmefixer12 жыл бұрын

    Thanks, Randy for the complete and leisurely coverage. Great video.

  • @aforman1951
    @aforman19512 жыл бұрын

    Again Excellant overview! Happy Thanksgiving everyone!

  • @gobfranklin6759
    @gobfranklin67592 жыл бұрын

    Wonderful job as usual. :)

  • @kirk8985
    @kirk89852 жыл бұрын

    Thank you 🙏

  • @DavidJohnson-tv2nn
    @DavidJohnson-tv2nn2 жыл бұрын

    South pond area -- @ 12:34 Concrete poured in pond outfall/overflow structure. @ 13:43 Metal deck pan placed on top of splitter box to pond outfall structure. Geofoam blocks placed behind retaining wall. @ 14:30 Metal deck pan placed on top of splitter box. Access hole will be cut later. Extra panels off to the side in case they "F" something up :)

  • @dalerichardson7202

    @dalerichardson7202

    2 жыл бұрын

    Hi David, I haven't been paying too much attention to these ponds...... Are South and East ponds we are seeing being designed to not be ponds? Looking at them the past few days, it looks like the design is set up so that runoff flows into them, percolates through multiple levels, and then exits out the bottom into the river, therefore never really being ponds in the traditional sense, just bio water percolaters........ So we shouldn't be seeing any standing water, unless it is shortly after a rainstorm. Is this interpretation correct?

  • @DavidJohnson-tv2nn

    @DavidJohnson-tv2nn

    2 жыл бұрын

    @@dalerichardson7202 Correct for the east pond. But... The water the water percolates to a collection grid and into the outfall channel. Which drains into another existing pond. Not the river. The South pond is different. It is a wet pond with a waterproof liner. So under normal conditions, the only way water can leave the pond is through evaporation or out the three 1' overflow orifices at an elevation of 6'. The pond overflow connects to one of the river outlet pipes. During a normal rain event, water moves through the pond and out the overflow. The pond has a surge capacity and can rise to 13' in heavy rain. At 13' water begins to flow over the weir in the splitter box, and out the river outlet pipes. Cutting off any further rise in water level in the pond. After the rain stops, water in the pond continues to flow out the overflow drain until it drops back down to 6'. Waiting for the next rain.

  • @BrianM853

    @BrianM853

    2 жыл бұрын

    @@DavidJohnson-tv2nn if the south pond holds water, why all the topsoil?

  • @dalerichardson7202

    @dalerichardson7202

    2 жыл бұрын

    @@BrianM853 Yes, this is what drove my question......

  • @dalerichardson7202

    @dalerichardson7202

    2 жыл бұрын

    @@DavidJohnson-tv2nn Thanks! See Brians question as it is mine as well.

  • @gabesander
    @gabesander2 жыл бұрын

    That black top lot had medians for like 35 stall supercharger

  • @TheElectricMan
    @TheElectricMan2 жыл бұрын

    thanks randy for another great video

  • @davidfidler1174
    @davidfidler11742 жыл бұрын

    16:09 I think this asphalt might be the test track? It’s close to where the finished cars will exit and they’re going to need a test track very soon!

  • @patrickkenny2077

    @patrickkenny2077

    2 жыл бұрын

    Very possible.

  • @DavidJohnson-tv2nn

    @DavidJohnson-tv2nn

    2 жыл бұрын

    The site plan indicates parking unless changes were made.

  • @sammyk874

    @sammyk874

    2 жыл бұрын

    Wouldn't be surprised if they used COTA for testing.

  • @GrantHodgsonWnNZ
    @GrantHodgsonWnNZ2 жыл бұрын

    Are they getting curved glass windows on the corners? Great shots Randy , nice to have you back, I am learning patience waiting for signs of production starting while watching the inexorable progress!

  • @TESLAenjoyer

    @TESLAenjoyer

    2 жыл бұрын

    No

  • @kevinstenger4334
    @kevinstenger43342 жыл бұрын

    What’s the next building going up? That’s a lot of steel they have staged.

  • @ItsLilRobs

    @ItsLilRobs

    2 жыл бұрын

    Battery cathode plant

  • @mvaottawa
    @mvaottawa2 жыл бұрын

    15:19 Crowded skies - another drone's shadow can be seen

  • @LACHIVA1969

    @LACHIVA1969

    2 жыл бұрын

    Brad's drone

  • @musaran2

    @musaran2

    2 жыл бұрын

    Not seeing it.

  • @shortaybrown
    @shortaybrown2 жыл бұрын

    How far along is the inside of the factory compared to GigaBerlin ?

  • @davidanalyst671

    @davidanalyst671

    2 жыл бұрын

    berlin workers sleep 4 hours in the afternoon, and they only work until 4pm

  • @jbbuzzable

    @jbbuzzable

    2 жыл бұрын

    My guess is Berlin since they had a head start and have continued work. Permitting seems to be the bottleneck. Although it appears both factories will begin production at about the same time, I predict that Berlin will ramp more quickly because of that.

  • @shortaybrown

    @shortaybrown

    2 жыл бұрын

    @@jbbuzzable - oh definitely....I know Berlin is ahead of Austin, but I saw the recent 2:30min video about inside GigaBerlin, and it looked amazing, completely finished. I just wondered if the Texas factory had all the lights installed inside, and it’s all painted white and there are lots of robots and work stations along the production line like in Berlin. I’m also excited to see the video of the inside of the full scale battery factory, whenever they decide to show that.

  • @texan-american200
    @texan-american2002 жыл бұрын

    19:35 On the left side of the screen, what is that fountainhead all about? Is it an aerator, or is it for some other function?

  • @musaran2

    @musaran2

    2 жыл бұрын

    Aerator, according to previous discussions. Since it is there the pond seems noticeably greener.

  • @DavidJohnson-tv2nn
    @DavidJohnson-tv2nn2 жыл бұрын

    @ 16:09 My guess is that single power pole sticking out into parking area will be removed at some point. Lack of provision for any landscaping between building and TxDOT property sucks! Architect responsible for design in this area, and around the building for that matter, should be replaced in my opinion!

  • @patrickkenny2077

    @patrickkenny2077

    2 жыл бұрын

    There will likely be some kind of retaining wall and stepped vegitation

  • @DavidJohnson-tv2nn

    @DavidJohnson-tv2nn

    2 жыл бұрын

    @@patrickkenny2077 I agree, but there is still a wide strip with no vegetation, unless changes are made. Right now, from the building going west, there is.... Parking ---> Road ---> More parking. No room for a single blade of grass!

  • @ItsLilRobs

    @ItsLilRobs

    2 жыл бұрын

    I was told by Elton Ray that the single power pole you are talking about supplies power to the stormwater lift station and will likely not be relocated

  • @patrickkenny2077

    @patrickkenny2077

    2 жыл бұрын

    The conduits installed a while back that cross the road by the south pond are for three utility circuits; I’m sure all the wood poles around the factory will go before too long.

  • @Bill_N_ATX

    @Bill_N_ATX

    2 жыл бұрын

    While I like pretty property as much as the next guy, for a car factory I'm not sure that the landscaping is high on my priority. Residential? A shopping mall? Some place that goes public goes, well maybe. But a factory. Plus, there was never going to be a lot of room and if you are traveling the toll road you won't see it anyway because of the elevation difference. So save the money for other areas. Like the entrance roads etc.

  • @RoyPanka
    @RoyPanka2 жыл бұрын

    Top

  • @scottmitchell2012
    @scottmitchell20122 жыл бұрын

    Where’s Randy? I hope all is well.

  • @gentlestorm
    @gentlestorm2 жыл бұрын

    Do all factories have such huge water management systems around them?

  • @jbbuzzable

    @jbbuzzable

    2 жыл бұрын

    Not that I have ever seen.

  • @gentlestorm

    @gentlestorm

    2 жыл бұрын

    @@jbbuzzable Maybe this area has regular heavy rainfall and flooding.

  • @davidanalyst671

    @davidanalyst671

    2 жыл бұрын

    not in the USA but in austin they do because it rains like a MFer in austin in May. They have a rainy season where it will rain an inch every day for a month. Go back and look at the end of may videos from this year. they had puddles 50 feet across, and they didn't do anything about them. Batteries use water to wash the battery rocks around? I don't 100% get it, but batteries do use water.

  • @jbbuzzable

    @jbbuzzable

    2 жыл бұрын

    @@davidanalyst671 What improvements would you suggest?

  • @jbbuzzable

    @jbbuzzable

    2 жыл бұрын

    @@gentlestorm I recall a meeting where the Austin water management board was reviewing the Tesla permit application. They were mostly concerned with the water retention plans as the Texas megadrought from a few years ago was fresh in their minds.

  • @majstealth
    @majstealth2 жыл бұрын

    at this speed giga berlin would be done already

  • @TESLAenjoyer
    @TESLAenjoyer2 жыл бұрын

    He’s back! First

  • @backlash00
    @backlash002 жыл бұрын

    Questions: Where will the cars (trucks) exit the building? Where will the test track be? And, were will cars line up for transport? Bonus: Will Tesla ship care out of Galveston? Your thoughts.

  • @davidanalyst671

    @davidanalyst671

    2 жыл бұрын

    Cars come off the "general assembly" line. California factory has like 6 general assembly lines, so the cars roll out every door they have. Elon built this cause its close to austin, and austin loves tesla cars. the rich nerds in austin love teslas. the only issue with this factory is that its not super close to a railroad, which would mean it could move cars easier and faster.

  • @midnightstar4065

    @midnightstar4065

    2 жыл бұрын

    @@davidanalyst671 Tesla had a bad experience using railroads in Fremont so probably doesn't mind...

  • @acmefixer1

    @acmefixer1

    2 жыл бұрын

    @Backlash Joe Tegtmeyer's Thanksgiving video goes into all the details you asked about. Watch it.

  • @eltonray2934

    @eltonray2934

    2 жыл бұрын

    I think at the present time the focus is on producing products. They have about 3,000 acres of land and they can build anything required as they ramp up production.

  • @Bill_N_ATX

    @Bill_N_ATX

    2 жыл бұрын

    @@davidanalyst671 there are two different rail lines about 5 miles away but Tesla doesn't usually move cars via rail. As for Galveston, you have the Port of Houston which is much bigger and has car handling facilities. They could also use one of the other ports if the wanted to build something for exclusive use.