Earned Value Management - Schedule Variance for the PMP Exam based on the PMBOK Guide 6th Edition
In this video Aileen explains the term schedule variance (SV) as it relates to earned value management for the PMP Exam and earned value analysis for the PMP Exam. The topics of planned value (PV) and earned value (EV) are also covered. Several PMP Exam Prep Questions are reviewed including earned value diagrams.
#earnedvalue #pmpexam #PMP
To join Aileen's email list and receive access to other free videos please go to: www.aileenellis.com
Aileen Ellis, PgMP®, PMP®, is an expert on project management. She is the owner and proudly the only instructor for AME Group Inc., a Registered Education Provider (REP) through the Project Management Institute (PMI). She personally instructs project managers to gain the confidence and knowledge to pass the PMP® Exam and the CAPM® Exam. She has helped more than 10,000 professionals obtain their PMP® certification and over 1,000 professionals obtain their CAPM® certification. Working with thousands of students from dozens of countries, Ms. Ellis has gained a thorough understanding of the ins and outs of A Guide to the Project management Body of Knowledge (PMBOK® Guide), the exam content, and proven test-taking strategies.
************************************
Want to hire Aileen to help you pass the PMP® Exam?
Contact Aileen at aileen@aileenellis.com
Aileen runs live face to face workshops as well as provides online coaching for very motivated individuals.
************************************
Social
**************************
My website: www.aileenellis.com
• Earned Value Managemen...
Пікірлер: 26
Hello all. I hope you like the video - Earned Value Management - Schedule Variance for the PMP Exam based on the PMBOK Guide 6th Edition. Tell me what you struggle with the most as it relates to earned value and maybe I can create a video to help you.
@vidhyarajupalepu1804
4 жыл бұрын
Thank you so much for helping aspiring PMPs like myself; I feel like I have a gotten a new PMP mentor, I will keep watching your videos to become a better project professional.
@AileenEllisPMPPgMP
4 жыл бұрын
@@vidhyarajupalepu1804 . You are welcome. Are you studying for your PMP credential right now? My KZread videos can really help you.
@vidhyarajupalepu1804
4 жыл бұрын
Aileen Ellis Thank you for your quick Reply! Yes I am preparing for my PMP and I stumbled across your videos and website last nite...they are so helpful..Thank you for doing this to the PMP learning community 🙏🏽
@AileenEllisPMPPgMP
4 жыл бұрын
@@vidhyarajupalepu1804 . Great. I hope you signed up for our email list so that you will get invites to live online training. www.aileenellis.com/ We have a live session scheduled in about 22 hours.
Helpful video. Earned value is critical to my job and employer. I passed the PMP exam but will keep watching Aileen's videos to maintain proficiency.
@AileenEllisPMPPgMP
4 жыл бұрын
Dave... first I am so happy to hear that you have passed the PMP exam using my online self study program. What a wonderful accomplishment. Second, I realize that earned value management is part of your job and for you to spend time watching my video on earned value makes me feel great. keep coming back.
Aileen, thank you so much for putting this information out! Your way of explaining makes understanding the concepts so much simpler. I'm taking the test in 10 days. I've already taken 2 practice exams and passed and am now going over many example questions using the formulas, including EVM, and am using your videos to get more proficient. I've used Head First PMP, PMPrepCast and the simulator, and of course the PMBOK Guide. I also got your kindle books to help me with specific areas. So helpful! Thanks again. :)
@AileenEllisPMPPgMP
4 жыл бұрын
Remember there will be very few math questions on the exam. Let me know if you want more help from me. I have a great program to be used the last week of studying. aileen@amegroupinc.com
VERY CLEAR AND WORTH YOUR TIME!
@AileenEllisPMPPgMP
4 жыл бұрын
Great to hear!
This is such a great explanation! Easy to understand. I am so glad I found you through LinkedIn!! Thank you for all that you do.
@AileenEllisPMPPgMP
3 жыл бұрын
You are so welcome! Sign up for free live training at: www.aileenellis.com/
Very grateful madam!
@AileenEllisPMPPgMP
2 жыл бұрын
Glad it was helpful!
I never thought PMP would be an easy ..You’re amazing ...
@AileenEllisPMPPgMP
4 жыл бұрын
Thank you. Sign up for free training with me at: www.aileenellis.com/
Excellent explanation. I would highly recommend Aileen video tutorials and sample questions. 👍
@AileenEllisPMPPgMP
4 жыл бұрын
Great suggestion! :) Thank you. Go to www.aileenellis.com/ and sign up to our email list for free training.
Very good explanation!
@AileenEllisPMPPgMP
4 жыл бұрын
Thank you.
You are very good Aileen!
@AileenEllisPMPPgMP
4 жыл бұрын
So glad my videos are helping you. When are you planning on testing? How is your studying going?
@rachitad600
4 жыл бұрын
Hi Aileen, I have it planned in August and I need to really do lot of tests . I really liked the way you explained EVM in simple English- it’s like you make every difficult thing simple, and we never realize omg that was so hard but when you say it appears simple 😊
I will soon be taking the CAPM exam. Your videos have been WAY more helpful than the course I took for my 24 contact hours. Do you have any tips for passing the exam? You are easily one of the best teachers on youtube and my favorite by far.
@AileenEllisPMPPgMP
4 жыл бұрын
You can do it! Glad it was helpful! Sign up for free training with me at: www.aileenellis.com/