Blue line | ORR METRO | K R Puram to Silkboard APR 2024 Updates

Blue line | ORR METRO | K R Puram to Silkboard junction APRIL 2024 Updates
Phase 2A - Silk Board to K R puram & upto Baiyappanahalli Depot - 19.603 KM
ಬಿಎಂಆರ್‌ಸಿಎಲ್ | ಸಿಲ್ಕ್ ಬೋರ್ಡ್‌ ಜಂಕ್ಷನ್‌ನಿಂದ ಕೆ.ಆರ್‌.ಪುರ | ಒಆರ್‌ಆರ್‌ ಮೆಟ್ರೊ
***********************************************
APRIL 2024 Updates
Recorded Date : 06-APR-2024
Civil Contractor :
PKG1 - AFCONS Infra - 9.859 KM & 2.84 KM of loops and ramps of SB Junction improvement
PKG2 - Shankaranarayana Constructions PVT ltd - 9.744 KM
ಸಿಲ್ಕ್‌ ಬೋರ್ಡ್‌ನಿಂದ ಕಾಡುಬೀಸನಹಳ್ಳಿಯವರೆಗಿನ ಪ್ಯಾಕೇಜ್‌ -1 ನಿರ್ಮಾಣ ಗುತ್ತಿಗೆಯನ್ನು ಆಫ್ಕಾನ್ಸ್‌ ಸಂಸ್ಥೆ ಪಡೆದಿದ್ದರೆ,
ಕಾಡುಬೀಸನಹಳ್ಳಿಯಿಂದ ಬೈಯಪ್ಪನಹಳ್ಳಿಯವರೆಗಿನ ಎರಡನೇ ಪ್ಯಾಕೇಜ್‌ನ ಗುತ್ತಿಗೆಯನ್ನು ಶಂಕರನಾರಾಯಣ ಕನ್‌ಸ್ಟ್ರಕ್ಷನ್‌ ಪಡೆದಿದೆ.
Stations in the stretch :
Central Silk Board Station ( Interchange with Yellow line ) : All pier cast up to concourse level. CC Connector erection in progress
HSR layout Station : All pier cast up to concourse level. CC Connector erection in progress
Agara Station : All pier cast up to concourse level.CC Connector erection in progress
Ibbalur Station : All pier cast up to concourse level.
Bellandur Station : Concourse slab casting works in Progress.
Kadubeesanahalli Station : All Piers cast up to concourse level.CC and PF arms being erected.
Kodibeesanahalli Station : All pier cast up to concourse level. CC and PF arms being erected.
Marathahalli Station : Concourse beam casting in progress.
ISRO Station : All piers cast up to concourse level.CC Connector erection in progress
Doddanekundi Station : All pier cast up to concourse level.CC Connector erection in progress
DRDO sports complex Station : U girder and I-girder erection in progress.
SaraswathiNagar Station ( Mahadevpura ): Concourse and platform slab casting works in Progress
K R Pura Station ( Interchange with Purple line ) : Concourse and platform beam being cast
#bmrcl #bangaloremetro #ORRMetro
------------------------------
Track: Dance With Me - Next Route [Audio Library Release]
Music provided by Audio Library Plus
Watch: • Dance With Me - Next R...
Free Download / Stream: alplus.io/dance-me-nr
------------------------------

Пікірлер: 34

  • @ChaitanyaSubhakar
    @ChaitanyaSubhakar3 ай бұрын

    Please make a progress video on the elevated section of the pink line as well.

  • @user-jj9rk7no1z
    @user-jj9rk7no1z3 ай бұрын

    Good effort... keep it up

  • @sachinjogi1995
    @sachinjogi19953 ай бұрын

    @sunilhp just a suggestion. it would be great if you could give a summary of all the changes. E.g., how many pillars have completed between stations. How many stations have completed in a line etc. that will be more informative to a wider audience. Maybe you can do that as a separate video since you’ve already spent quite a lot of effort in documenting videos of all this.

  • @SunilHP

    @SunilHP

    3 ай бұрын

    Hi Sachin, look for monthly updates from Maddy. Almost every month he too puts the updates. twitter.com/maddyvoldy/status/1774804840218280080?t=EVs3sTJcZqU2zB0rw6jVGQ&s=19

  • @KS-yk2mh
    @KS-yk2mh3 ай бұрын

    Superb capture. Detailed explanations. Fantastic, Sunil. Keep it up!!!! Appreciate your energy and eagerness to share the developments. Bhaarath Maatha ki Jai. Jai BJP

  • @vijethkumar6549
    @vijethkumar65493 ай бұрын

    Looks like Afcons are on their A game now. Finishing the work within this year end looks convenient. But for SNC it's looks like hurdle is for OWG and Doddanekodi railway over pass.. !! Your take on this @sunil h p ?

  • @SunilHP

    @SunilHP

    3 ай бұрын

    Yes. Both are doing well. Afcons needs to up their viaduct works. Snc unfortunately have 2 owg one here at doddanekundi and other at benniganahalli. At the mercy of railways now

  • @vijethkumar6549

    @vijethkumar6549

    3 ай бұрын

    @@SunilHP sometime I feel Bengaluru needs a seperate zone and come out SWR. They are most irritating people for our infra developments

  • @prasadanand1252

    @prasadanand1252

    3 ай бұрын

    @@vijethkumar6549 They won't do and won't allow others to do.

  • @SunilHP

    @SunilHP

    3 ай бұрын

    @@vijethkumar6549 true. They just have to be logical and accommodate local needs. Rigid guys always bring high handed. Kr pura station they are not parting land knowing well they are the biggest traffic causers there

  • @dvlogs6965
    @dvlogs69653 ай бұрын

    Ramps towards HSR and bommanahalli are small. They will become conjusted in future. Looks like 2 lane ls

  • @SunilHP

    @SunilHP

    3 ай бұрын

    The site at SB is very constrained. due to metros , flyovers on both side. existing flyover and a mega network of Storm water drains. This is what they were able to achieve with out shelling exorbitant price for land acq

  • @JCMenon76
    @JCMenon763 ай бұрын

    Thank you for bringing out the video updates, very informaive. 24:23 The high tension wires here would be lifted higher?

  • @SunilHP

    @SunilHP

    3 ай бұрын

    Has sufficient clearance for metro I believe.

  • @sathwickkiran2103
    @sathwickkiran21033 ай бұрын

    Hey! Why is there a delay in construction of the double decker flyover from SB towards BTM? We can hardly see anything happening on that part.

  • @SunilHP

    @SunilHP

    3 ай бұрын

    Double decker flyover is already completed and there are tests being conducted on the structure. for commissioning this, the loops and ramps at Silkboard has to get ready for which the dates are May-Jun 24 for A, B and C loops . Nov 2024 for D & E loops.

  • @shreyass5664
    @shreyass56643 ай бұрын

    Thanks of uploading👍.I think first silk board to kr puram line will open first

  • @A7270_

    @A7270_

    3 ай бұрын

    It will as it is under phase 2A and is proposed to open with pink line of namma metro in early 2025

  • @prasadanand1252

    @prasadanand1252

    3 ай бұрын

    @@A7270_ Pink Line itself will open only in 2025 ending as tunneling from KG Halli to Nagavara will finish only in November and they have closed Bannerghatta road near Lakkasandra for one year to construct the station. Do not expect them to launch anything before 2025 December,even the yellow line. I have seen enough delays.

  • @SunilHP

    @SunilHP

    3 ай бұрын

    It should be. They started work a good 6 to 8 months earlier

  • @MayurPrakash
    @MayurPrakash3 ай бұрын

    why are the pillars between hsr and silboard different from other areas(sqaure shaped instead of circular)?

  • @SunilHP

    @SunilHP

    3 ай бұрын

    These are along the lake bund and with a curve. So eccentric pier caps and piers

  • @MayurPrakash

    @MayurPrakash

    3 ай бұрын

    @@SunilHP ohh got it,thanks

  • @536sai
    @536sai3 ай бұрын

    Iblur station work is stalled for many months now. It might become another tin factory station. Any reason?

  • @SunilHP

    @SunilHP

    3 ай бұрын

    No particular reason that I am aware of. Earlier had stalled for reworking to accomodate SJP-Hebbal Line and then that designs were out. Now the piers are all cast to Concourse level. barricading has been done for second piers on the side. Concourse Cross Arm erection should start soon. Now that AFCONS have done this at Agara and half of HSR.

  • @soorajck3858
    @soorajck38583 ай бұрын

    Why no active work going on since last couple of months ?

  • @SunilHP

    @SunilHP

    3 ай бұрын

    Work is going on actively on both AFCONS and SNC part. Not sure which part you are referring to.

  • @JCMenon76
    @JCMenon763 ай бұрын

    20:45 What’s the plan here, the pier lengths are much shorter ?

  • @SunilHP

    @SunilHP

    3 ай бұрын

    These are design provisions for future sarjapura to hebbal line which will crossover from left to right here. For a change bmrcl being proactive.

  • @JCMenon76

    @JCMenon76

    3 ай бұрын

    @@SunilHP Okay, good to notice the proactiveness 👍

  • @JCMenon76
    @JCMenon763 ай бұрын

    5:06 Is there no station planned on the blue line at Tin Factory ?

  • @SunilHP

    @SunilHP

    3 ай бұрын

    Nope. No station here due to lack of space

  • @lohitjoshi2146
    @lohitjoshi21463 ай бұрын

    No AC busses in this route? In 2013 this road was fully dotted with AC vajra busses. There was 1500 AC busses.... now hardly 200.... This is the fate of congress ruled state.. Shame on congress,.

  • @SunilHP

    @SunilHP

    3 ай бұрын

    For what it's worth the buses are in this Fate due to procurement stoppage during BJP Rule. Now a lot of buses have been added and procurement raised for electric AC buses. Anyways let's keep politics aside and speak facts