Bangalore Metro : Blue line : Airport line : Hebbal to Tin Factory: JUN 2024
Blue line updates from Hebbal to Kasturinagar. Recorded Date : 09-JUN-2024
Phase 2B - Hebbal to K R puram
***********************************************
JUNE 2024 Updates
Civil Contractor : PKG1 - NCC LTD - 11.003 KM & 650 metr depot line
PKG2 - NCC LTD - 11.678 KM
PKG3 - NCC LTD - 15.011 KM including 718 meter cut and cover portion.
Piling Works Happening and Pier casting Picking up pace.
Stations in the stretch :
Package 1 :
Kasturinagar Station - Pier casting Upto Concourse level in Progress.
Horamavu Station - All piers cast up to concourse level.
HRBR Layout Station - Concourse Arm Connector affixing has begun.
Kalyan Nagar Station - Concourse Arm Connector affixing has begun.
HBR Layout Station - Pier casting in progress.
Nagavara Station ( Interchange with Pink Line ) - Piling In Progress.
Veerannapalya Station - RHS : Pier casting. LHS : Piling.
Kempapura Station - Median Pier rebar up. Side Pier works yet to begin.
Hebbal Station - Pier casting yet to begin.
ಬಿಎಂಆರ್ಸಿಎಲ್ | ಕೆ.ಆರ್.ಪುರ ನಿಂದ ಕೆಂಪೇಗೌಡ ಅಂತರ್ ರಾಷ್ಟ್ರೀಯ ವಿಮಾನ ನಿಲ್ದಾಣ | ಏರ್ಪೋರ್ಟ್ ಮೆಟ್ರೊ ಎರಡನೇ ಹಂತ-2B
Пікірлер: 13
Waiting for the day when we will travel to airport in metro 😊👍
Thanks for the update!!!
Can you add notes about differences between this and last month's updates. Will be helpful to know the pace of progress
@SunilHP
Ай бұрын
ok. will try and add from the next month
it will take another 5 years for the entire project to be completed. Airport to Hebbal with a distance of 25 kms Hebbal to Tin Facory distance is 17 kms Tin Factory to Marathahalli distance of 8 kms Marathhalli to Silkboard distance of 15 kms this project got approval in 2017 at a estimated cost of 4K Crores as on date with certain medians and fixing of arms it has come to 10,000 crores - as days go by and while it is finished it will come to 15K Crores. both State and Central are supporting the project Courtesy: kannada prabha - a unit of Indian Express Newspaper.
Very slow progress. Dont see it completing for another 2 years atleast. June 2026 if I am being optimistic!! As usual thanks for the video.
@UtkarshThakur-bx4oj
Ай бұрын
The timeline for whold metro blue line is 2027
Hi sir is there any improvement in the removal of the power line inbetween the pillars
i would like to know if you drive from airport to silkbosrd in one day and edit it over three days or you do it like segments
@SunilHP
Ай бұрын
No. Not in a single stretch. Depending on my travels, it is always in segments.
Bro after manyatha will the metro pass through underground to reach nagwara station
@SunilHP
Ай бұрын
No Nothing Under ground here. The metro pillars will be on the median of service road and ORR. So the Foot over bridge was dismantled recently. Work should start sooner.
@sairamlohith
Ай бұрын
@@SunilHP k bro