Project Scheduling - PERT/CPM | Finding Critical Path
This video shows how to
• Construct a project network
• Perform Forward and backward passes
• Determine project completion time
• Calculate slack values
• State the critical path
Node convention used based on:
Quantitative Methods for Business by David Anderson, Dennis J. Sweeney, and Willard Thorp
Пікірлер: 854
Guess who's passing their exam tomorrow because of this video.
@joshemman
3 ай бұрын
All the best on your exam, Hady.
@smoothlesst1981
2 ай бұрын
I am writing today😂 hopefully 6 min is all I need to pass
@kadianvangogh3435
2 ай бұрын
How was it? Mine is tomorrow
@essieokereke6594
2 ай бұрын
Mine is next week.😩
@hadytannir9248
2 ай бұрын
@@essieokereke6594 best of luck 💜
Mind blowing explanation. Such complex thing explained so easily in 7 mins. Thanks a lot. Saved a lot of my study time.
@EJA281
9 ай бұрын
Agree!! The video breaks things down so simple.
Damn! This is like one week of my lectures in just under 10 minutes. And guess what? I finally understand this stuff
@BehtiGangaofRandomness
4 жыл бұрын
haahhah
@BehtiGangaofRandomness
4 жыл бұрын
same here
@khurmiview
2 жыл бұрын
You are very right
You're so clear, straight to the point, not fast talking and the graphic is very good. Thank you so much, awesome job!!!
Mr Emmanuel, your videos are fantastic. Thank you so much for putting them out.
I have never done project management a day in my life but now I completely understand how to determine the critical path and duration... amazingly well done! Wow!
Great video. I am doing improvement work with my organization and you by far have the best video to help teach this topic online. Professional, detailed, and visual. Thank you.
I thought this topic was super complex but you made it very easy to understand. Wish every text book made this so easy to comprehend. Thank you!
I have watched so many videos in tears this was the only video that was able to explain this to someone like me who has no background in maths and freaks out at the sight of numbers. Thank you so much sir
This is by far the most understandable explanation I have seen👌. Thank you so much!
You are born to teach. So freaking concise and to the point. God Bless you Brother!!
Mind blown by how clear this explanation was. Thanks!
Thanks Joshua! This is one the shortest and the best explanation I have seen so far on youtube or anywhere else! You are a rare breed of best teachers!!
Only if you know how many times you've saved my life and gave me good marks on my finals and midterms " statistics, project, and many other classes" i've always dependent on you THANK YOU.
@tushar3549
2 жыл бұрын
tai
Really shocking seeing such a major concept explained in such a short time. Thanks a lot for the clarity.💯💯💯💯
You're so good at explaining these concepts. Thank you so much!
WOW!!! I've been studying Project Management forever...Joshua Emmanuel you are phenomenally well spoken and articulated this subject matter to the pinnacle of perfection, thank you so much, you have a nee subscriber for sure!!
Thank god I landed here in very short span of time to know what is PERT and CPM looks like. This video is so useful, informative and so easy to understand such an uneasy subject. Great work Joshua, Kudos to you
Thank you SO much for this visually aided explanation - it made so much more sense and the info sink in faster than most other videos.
Seriously...! The best ever explanation I've had on CPM. Thank Buddy @Joshua Emmanuel.
Bro this may be one of the BEST videos on KZread. I’m starting a PM job and this just gave me a boost of confidence. THANK YOU
@yushaq2434
3 жыл бұрын
God give you success in your new career. This guy is a life saver.
We need more of such videos. Detailed and thorough. Thank you once again.
@MathHandsOnwithPython
Жыл бұрын
Also, find Python solution for CPM kzread.info/dash/bejne/e2qBrq2GmdXAYqg.html
Thank you! Now it's time to have my midterm in an hour :D
@ARJUNMANCHIKALLU
4 жыл бұрын
Same here
Best explanation I've heard. Taking Udemy course and couldn't get crtitical pathways. Looked it up and had hard time until I saw this video. You are amazing.
I'm very glad that I found you. Everytime I watched your videos, it helped me to easily understand my subjects. Thank you so much!
I owe you a cup of tea,,,,,,cant get any better explanation than this
That was the easiest yet the most effective explanation. Thank you. Truly helpful.
Thank you soooo much for this!!! I have my finals starting tomorrow, and this one's coming out as my first paper 😭 the best explanation i could ever find in youtube, God bless your soul 😩🙏🙏
OMG, thanks a bunch. Once again, Joshua to our rescue!
Thanks. This is surely the best video on understanding CPM. Very clear and professional. Job well done!
Such a clear and straightforward presentation of the information. Thank you!
Great! That's a short, precise and clean explanation, thank you for the video.
Simple and straight forward, you have a thumbs up from me and I'm sharing your link to my whole class
you explain this WAY better than my management lecturers. i finally understood. thank you!
You're the man, Joshua! Thank you for helping us with another class.
@joshemman
Жыл бұрын
My pleasure!
THIS IS THE BEST EXPLANATION! It is very detailed. THANK YOU SO MUCH!!!!
The explanation I got for this was incomprehensible, so this helps a lot.
Wow just Wow, best and most simple explanation....I have just finished half a year in construction planning and couldnt get my head around moving forward and then back to calculate slack time. After watching this I will be ready for my exam next week...Thank You!
I was so confused in how to obtain the critical path before watching this video. Thank you very much, your explanation was extremely helpful!
Beautiful one my brother .... wish I had this some 30 years ago doing Applied Maths at University. Nice and quick revision for my PMP. Thanks!
Hello and courtesy was great for me I studied with the teacher for 3 days, but I didn't learn anything, even though I don't have good English skills, all my problems were solved by watching your video once. Thanks a Million
This has got to be the clearest explanation on critical path ever... thank you!!!
@jeffballa4474
5 ай бұрын
What he said🙏🏽🙏🏽
Extremely helpful video Sir, it made the PERT look so easy and interesting. Keep making this kind of stuff...
Thanx a lot for this video. It's really the best explanation on KZread - I wish our prof could be as good as you in teaching PM))
@elianjandongan8583
5 жыл бұрын
Lol Same
@sairkhanniazi3707
5 жыл бұрын
Need to talk with you...
@arvichesterancheta8664
3 жыл бұрын
Same thoughts
@delaredoo77
3 жыл бұрын
forreal tho!!!
@sadhikakalra4810
3 жыл бұрын
Correct thank you so much you’re amazing.
I got a perfect score on my exams because of this, thanks!
You explain it in a very easy understanding way. Thanks a lot!
By far, the best tutorial on KZread for Critical Path. And it's only 6 mins.
Excellent brother, very useful for me. the video describes exactly what I was looking for. you are a great teacher.
Man, I hunted throughout youtube for a video that could explain this. You did it beautifully.
@joshemman
8 ай бұрын
Thank for dropping a note, my friend.
@Plookiss
3 ай бұрын
me too :D
Suuuuuuper helpful!!!! Thanks a lot!!! I couldn't tell how much I appreciate your video. It's beyond words!!! A million thanks to Joshua.
Stellar video! Remarkably helpful. I don't usually comment on videos, but for this, I had to make a deserving exception. Keep up the good work!
What an explicit video. You are an academic hero
Bros....you sabi! Thanks a lot. The best and most simplified explanation ever.
Incredibly clear description. Thank you!
The best explanation for constructing a project network. Very helpful. Thank you so very much.
It is the best explanation without any suspicion!
Absolutely superb. Said everything simplistically and in bite-sized portions to help us understand. Easily the best video I've seen on this topic
@joshemman
Жыл бұрын
Glad it was helpful!
Thank you so much. So much clearer than the online class I'm taking.
So informative. I am so grateful to you, Joshua!
Now, I can finish my homework. Thank you so much!!!!
This has been the best explanation on the topic. Thank you.
Thank you for the video on Project Scheduling. I took a construction class on Scheduling and Planning at the Community College of Baltimore County in Catonsville, Maryland in 2017.
Thank you so very much, for an very clear and easy to follow video. If only more instrutors could be as clear and make things so easy to follow along, we might have less problems.
Thank you very much, this is the best CPM video I have ever watched. God bless you!
Joshua's explanation is simple and easy to follow.
What an incredibly well done and succinct explanation
better than my lecturers Honestly.. Thank you. I understand this so much better now
Mr Emmanuel, your videos are fantastic. Thank you so much for putting them out.. :)
Thanks a bundle. The best explanation in shortest possible time
I pulled my hair out (almost) from frustration trying to get this concept, and you explained it so well! Thank you so much!
@edutechguruengineeringlear4280
Жыл бұрын
kzread.info/dash/bejne/i4iW0siknarKe9o.html
Thanks Joshua. This has been a big help a few days before my final!
Thank you for this video, it's amazing how easily you explained something so complex
incredible explanation. Short and precise. going to watch more of your vids.
Phenomenal video bro, simplified everything and the diagram and definitions helped heaps!!
Best explanation ever, struggled with this but got it now. Thank you.
I'm studying for an exam, makes so much sense then the reading material, thank you
I watched this video 5 times because you explained it soooo well. OMFG thank you!
Valuable explanation, therefore a valuable contribution. Thank you so much!
PROF! U JUST TEACHED ME SOME ENTIRE LECTURE IN LESS THAN 7 MINUTES NOW THIS IS SOME GOOD OJ MINIMIZATION
You did a fantastic job explaining how to do critical path! Thank you!!!!
You saved my life 2 hours before my exam today. God bless you.
Brilliant explanation, didnt think i could understand all of this in less than 7 minutes
This is a great video, I was racking my brain to understand what my prof was saying, watched a few youtube videos until I came across yours. Thanks a lot.
I keep on visiting this video as it is the best video , so far to learn and understand ......Thanks for sharing Joshua
Such a clear and simple explanation. You are a good teacher
Dude, you are a legend. I got through my stats class because of you. You deserve more subs!
Thank you very much for such a simple and effective explanation. All the best !
Am from Uganda, going for my project management assessment this week and browsed through for an explanation of this thing, u did it best dear, I can't thank you enough sir
Lucky for this new generation. Studying for them is very easy with so much free information with variety of examples and explanations in the youtube or google. Unlike before the advent of internet where students relies on the book with minimum information.
Really well explained. I was stressing about how will I understand CPM calculations but this video cleared my concept. Thank You.
I have been asking so many questions with our instructor about this, but only your video explain very well, in a manner were it is just like, 1+1=2! Kudos to you bro!!
Awesome Professor Emmanuel. Glad I found your video
Thank you sir! For making this topic crystal clear!
Thanks for the video, this makes this now simple concept much easier to understand than how text books explain it. Thanks!
You helped me time ago with programming; I had no idea you did project planning for engineers as well. Best on KZread. I may dedicate my degree to you, sir!
What a great explanation. Thank you man. May God bless you🙏🏾.
You are awesome! I have been struggling to understand this, but you broke it down. Amazing.
What a perfect short and up-to-point explanation of the critical path. do the same for the other model, it interest and reflects
Little note to anyone. Even if you start on day/week 1 instead of 0, it still works. thanks Josh!
I didn't need any subtitles; your voice is clear. I didn't need any additional reading in the midst of the playback; your elaboration is clear.