The allocation structure in internal order settlement allows us to choose the level of detail to see in the receiving cost objects after the settlement. In the allocation structure, we map the different cost elements to secondary cost elements for settlement (category 21) and we also select which cost elements are to be settled using the same source cost element (primary cost element).
In this video, I explain the concept of the allocation structure with a demo on SAP S/4HANA 2023. The demo includes:
- Configure Allocation Structure
- Create secondary cost elements for settlement
- Manage internal order master data
- Define order settlement rule
- Run settlement with allocation structure
- Display internal order and cost center reports.
The configuration manual is available to elite and platinum members. To become a member check this link www.youtube.com/@abdullahgala...

Пікірлер: 9

  • @chiit70
    @chiit705 ай бұрын

    Very good and useful vedio

  • @AbdullahGalal

    @AbdullahGalal

    5 ай бұрын

    Glad you liked it

  • @jamal_jaja
    @jamal_jaja5 ай бұрын

    Is there any video explaining how we can connect SAP data into Microsoft access ?

  • @AbdullahGalal

    @AbdullahGalal

    5 ай бұрын

    No, I don't know how this works

  • @rexsu9202
    @rexsu92025 ай бұрын

    Dear Sir, it's a very useful content, however I am wondering if you can share the reason why there is another folder named " assessment cost element " while you already set secondary cost elements in the folder named " settlement cost element " ? really really appreciate if you would like to share ! big thanks !'

  • @AbdullahGalal

    @AbdullahGalal

    5 ай бұрын

    Nice question! The allocation structure can also be used in the cost center cost assessment (allocation). In this case, the assessment cost element is used

  • @rexsu9202

    @rexsu9202

    5 ай бұрын

    @@AbdullahGalal Dear Sir, big thanks for your helpful response~

  • @AH-ky7xb
    @AH-ky7xb5 ай бұрын

    Hi, very informative video. In you scenario keeping everything else the same (all other cost elements), is it possible to settle one cost element say 310020 to 1) only one of the cost centers, or 2) split it 50-50 btw the two cost centers 1000 and 2000?

  • @AbdullahGalal

    @AbdullahGalal

    5 ай бұрын

    For that you can use a source structure. Check the source structure video in the playlist