CPM in Project Management & Operations Research | How to do a Critical Path Method
In this video, you will learn how to do a critical path method in the most easiest way.
CPM is an important scheduling technique. This method is used when the duration is known or certain.
The steps involved in CPM:
1. Network Diagram
2. Identify the critical path
3. Calculation of Early start time, Early finish time, late start time and late finish time.
4. Calculate the float, free float and independent float.
#CPM #Criticalpathmethod #freefloat #independent float #float
00:00 -Intro
00:43 -Network Construction
02:30 - Critical Path
04:59 -Early Start Time
06:04 - Late Finish Time
8:34 - Early Finish Time
09:08 - Late Start Time
09:57 - Total Float
11:02 Free Float
13:49 Independent Float
Keep Watching, Keep Learning
Пікірлер: 366
I always have mental block with this topic. But thank you very much for making it so clear, palatable, and easy to understand. You are an amazing educator!
@karpagamqtcorner8764
2 жыл бұрын
Kenzo I'm glad this video helped you .Stay tuned for more such videos
@kranthikumar4665
2 жыл бұрын
@@karpagamqtcorner8764 float and slack both r sam ma'am?
@karalmarks238
Жыл бұрын
@@kranthikumar4665 yes
@hemantkumar5347
Жыл бұрын
pl
@bridgetzulu619
10 ай бұрын
Thank you 💕
very nice video. tomorrow is my exam
@AmazingModernTech
3 ай бұрын
Same bro
@aniketghosh2001
3 ай бұрын
Us bro
@04_ritampaul87
Ай бұрын
Today is my exam, I am in bus going to college and watching this video
@93two2five9OO6SIX
Ай бұрын
Can u share the question paper?@@04_ritampaul87
Thanks for watching the videos. The chapters are added here. 00:00 -Intro 00:43 -Network Construction 02:30 - Critical Path 04:59 -Early Start Time 06:04 - Late Finish Time 8:34 - Early Finish Time 09:08 - Late Start Time 09:57 - Total Float 11:02 Free Float 13:49 Independent Float Keep Watching, Keep Learning
@kranthikumar4665
2 жыл бұрын
Ma'am slack and float both are same?
@user-vo5bs2tr6e
5 ай бұрын
maaam the duration from 1 to 2 is 12 not 13
had an exam today, watched this video yesterday with 0 prior knowledge and still managed to nail these problems correctly. Great Video, Came back here to say Thank You!
Simple and great teaching. I never understood clearly this topic either during my college days or during my service till today. You made so clear . Thank You Madam.
thanks dear porf god blees you two days i was watching the different videos related to this lecture. fortunately your lecture solved my problems in 10 minutes .
YOU ARE SO ORIGANIZED AND GENIUS TEACHER. IT'S WOW!
Watched so many vedeos regarding free float,total float, indipendent float. But can't get it untill I see ur vedeo.Finally I understand this topic. Thank you for your excellent explonation.
This is fantastic. Learning it online and you've made it easy for me to understand 👍
Hi Miss, I from Malaysia. I really appreciate that finally I can find someone with good knowledge and widely share. Thank you 😊
It didn’t took even 5 minutes to understand. Thank you ma’am
Greeting from Kenya. This is very simple to understand. Thanks very much for the clarification 🙏
Thank you, Madam..for your wonderfull explanations..Helps me lot for my MBA in Engineering Management exam. I was little confused...you explains better..Love from Malaysia.
Madam 1 day before exam me video chusa....aboo ma teacher 1week cheppina Ardham kaanidhi meeru vanna rasinattu chepparu .....tq you very much Madam❤️❤️......
you are an amazing tutor ,, thanks for making it so simple to understand
The best explanation for self study students. Very easy to understand
Wonderful explanation, each and every step is clearly explained! Thanks Ma'am.
I am having an exam related to topic and was confused with the formulas. Thanks to u mam now I am clear with everything. The topic was taught very clearly and easy to understand. You are doing a great job and please continue helping people with your way of teaching.
@karpagamqtcorner8764
2 жыл бұрын
Glad to hear that Santhosh.
I didn't understand it in my class. I also found it very boring. But this is now very clear and enjoyable to me. Thank you for this amazing video!
I forgot I saw this and realized it again...Thank you ㅠㅠ
Thank you Ma'am for this easy-to-understand video tutorial.
Tomorrow is my exam i have no one to help me so you are my only hope
Thank you mam .... i do not understand cpm example but,your support and explaination are understand example
I always have mental block with this topic.but thanks for making it clear and easy to understand. Your educating method short, precise, easy and very simple to understand....You're unstoppable
Madam 1 day before exam me video chusa....aboo ma teacher 1week cheppina Ardham kaanidhi meeru vanna rasinattu chepparu .....tq you very much Madam......
Thank you so much It's very easy to learn! It's help me alot ❤️
I love the way She made everything easy, I understood everything She said.
@karpagamqtcorner8764
2 жыл бұрын
My mission is to break complex concepts into a simple concept. I'm glad that you have enjoyed the video Unathi Febane .
Getting you very well from Tanzania” Mathematics Unite all the people despite our differences”
@karpagamqtcorner8764
2 жыл бұрын
Indeed it is true Obilla Ezra
Your teaching, is so amazing. Am so clarified and refreshed by your teachings. Thanks alot
Urs teaching way is easy understand by this topic mam... In my clg my mam doing this topic I felt fear how to do but I saw this vedio easily I understand ..tq so much mam
Thank you maam for explaining this topic beautifully in 16 mins. i was facing problem while understanding this topic and reading the boring ppts
It is really well-explained ma'am, thank you so much ma'am for this video. The method of study is very simple and more effective than others.
Watching this a couple of days before CMA Finals.... And this is the best video I've come across for network analysis.... Thanks a lot ma'am 🙏
@alishakashyap4431
Жыл бұрын
Same here😅.. All the Best!!
@hariharanganesh9790
Жыл бұрын
@@alishakashyap4431 You too!!
Just the perfect explanation.Thank you
mam, you have explained it soo clearly and politely, thanks
Ma’am i am sufaila. Thank you for such an amazing video❤you made the concept simple n easy to understand! Now i got a clear picture about cpm, all credit goes to you!
Good afternoon, I am a Ghanaian from West Africa, and I really enjoy your presentation.
This is on point. Thank you 🙏
TQ mam I have understood very clearly it is very useful for my exam mam
This is fantastic. Learning it online and you've made it easy for me to understand
@karpagamqtcorner8764
2 жыл бұрын
Glad to hear that George Ogalo
Thank you so much! Extremely helpful!
The clarity of mam's teaching is remarkable
The best explanation for self study students. Very easy to understand. Thank you Ma'am.
@karpagamqtcorner8764
2 жыл бұрын
Glad to hear that Kaushini
This problem process after 5 mins heading is rounding.. Super telling mam thank you so much
Thank-you very much,concept become crystal clear.
Thank you so much mam 🎉❤️ very clear and easy explanation 💫just perfect 💯😌
I will follow your learning video always, but a great thank's for this topic. Thank you so mach.
@karpagamqtcorner8764
2 жыл бұрын
You are most welcome Amanuel Getaneh :-)
Thank you ma'am your video is really helpful for me 😊 the day after tomorrow is my exam 😃 so thank you 😊
Thank you so much mam.Your video is most important to understand this CPM Method easily and after seen this video now i will solve all type of sum in this method.Once again thanks a lot mam.😊🥰
Simple and clear networking am done thank you so much mum
Thank you so much Ma'am -- Very Nicely clearing the concept.---"Hope This is the best way you teach".
@karpagamqtcorner8764
2 жыл бұрын
Thanks for liking. Stay tuned for more such videos
❤❤❤ Thanks very much for the precise procedure ...easy to understand and lovely
Thank you very much ma'am. I'm subscribing. I have an exam tomorrow and this really helps❤
The way of teaching is brilliant 💓thanks alot
You are amazing ma'am. Thank you so much. Lots of love.❤
Very clear teaching. Thank you
That was very well done,.. easy and simple, you get my subscription
Thank you so much mam, i have understand the concept of this math Very clearly. Thanks again mam
@karpagamqtcorner8764
2 жыл бұрын
It's my pleasure Julekha Juthi
Thank you so much ma'am Very useful for cma final level costing
Very informative video !!! Thank you
thank you mam for the video , its simple to understand this topic through this video .
Thank you, it's clearly understood
Thanku ma'am for that much simpler explanation 👏👏
By the name itself CRITICAL everyone becomes nervous(😂), but watching ur vedio, they certainly felt that its very easy method... Awesome explanation Mam....
Thank you so much Madam, it is so easy to understand. Thank you. Have an exam in 4 hours lol.
@karpagamqtcorner8764
2 жыл бұрын
Glad it was helpful!
OMG!! Thank you so much ma'am! finally i understood this topic!
@karpagamqtcorner8764
2 жыл бұрын
Most welcome 😊
You are a good Teacher. Very good explanation. thanks
@karpagamqtcorner8764
2 жыл бұрын
You are welcome!
I like your way of teaching.
Very nice work! Thank you so much ma'am!
@karpagamqtcorner8764
2 жыл бұрын
Thank you too! Keep Watching
This is a nice asynchronous learning
thank you so much madam for this critical path method is teach very easily and i understand this method and i prepare for exam thank you so much mam
@karpagamqtcorner8764
2 жыл бұрын
All the best
I havr understood the concept very clearly thank u so much ma'am 😊
@karpagamqtcorner8764
2 жыл бұрын
Most welcome 😊 Vaishnavi R
Very helpful thanks for saving my semester
@karpagamqtcorner8764
2 жыл бұрын
You're so welcome! Madaraka Deche
with 20 minutes i got it clear, thanks mam. U said in independent float if the value is negative & u made it 0, the same is applicable for Total float and free float.Thanks in advance
Thanks so much I was able to understand this
Thank you for this video.
Very explicit Thank you very much ma'am
Mam very nice you are good 😊 teach .. I am very impressed thank you mam .. I like it this video .. I have clear doubts mam.. very thank you
You are amazing instructor ❤
thank you very very very....... Much Mam. This is very very..... Help full for me 🤗🤗🤗🤗🤗
for backward pass at step 2 , 26-15 = 11 is minimum , compared to 28-15= 13
@RParmar-hp6hl
3 ай бұрын
So what did you take 11 or 13??
@RParmar-hp6hl
3 ай бұрын
Because it make sense..jaisa forward process gya tha waisa hi backward jana chahiye and mam ne wo 2-4 wali line calculate nai kri jisse 11 Aa rha h minimum.. Ya to esa ho skta ki aage jake wo 11 - 13 krke - 2 ho rha hoga islie nai lia..?? Somebody clear me plz😭
@wierdoevents905
Ай бұрын
On the critical path i.e 1-2-5, there will be no float. Because it is already taking the maximum time, we cannot shift the start or finish without adversly affecting the end time i.e 28 . Hence logically the EST and LFT will be the same.
Most helpful .it's clearly explanation
Thank you,u where a great help., 🙏🙏
thank you very much to identify simple to more understand
Thank you for this amazing video!😍😍😍🌹🌹🌹
very easy to understand, thank you ma'am
thank you so much🥰, you taught it very well
thank you, the video is very informative and helpful
@karpagamqtcorner8764
2 жыл бұрын
Glad to hear that!
Thanks you so much you are amazing teacher.
excellent video... mam u r grt... have seen so many videos but didnt get it... aapke video me 1st time me hee aa gaya,.. pls do share more video or how to prepare Project plan video
Very good and easy to learn
Very clear video. Thanks
Thank you very much for nice explained
Very clarified way 🙏🏻
Thanks.. mam you teach it so easily 🥰
very east and good explanation, thank you
One more subscriber😂thanks from Kenya
Explaination excellent 👍👍
Well explained
I have exam tomorrow on this problem mam. But madam you solved my full doubt on free float thank you for that . Thanks you mam💚