In 2023, the PMP exam will feature a significant number of questions on Stakeholders. Also, the most challenging responsibilities of a project manager is to engage the stakeholders and keep them supportive.
Join Our Lead Mentor and Head of the Training Department Gautham Sudakar in this KZread live today where he will discuss the 5 most crucial stakeholders questions that will appear on the PMP exam. He will utilize techniques such as EDUHUBSPOT's world-famous Elimination Technique, the Neil Armstrong Technique, and the Einstein technique to approach these questions. Learn from the best.
To connect with Mentor Gautham Sudakar, don’t hesitate to write an email, his email id: gautham.sudakar@eduhubspot.com
To know more about EDUHUBSPOT PMI-Approved PMP Bootcamp, check out this link: www.eduhubspot.com/packages/pmp
Connect with us on WhatsApp: wa.me/message/XVI7DMTEACX7L1

Пікірлер: 13

  • @villageengineer518
    @villageengineer51810 ай бұрын

    Hi Gautam Have cleared my PMp September 1st.....I referred your videos and which helped lot

  • @raguramakrishnanb8346
    @raguramakrishnanb8346 Жыл бұрын

    GREAT learning session ❤

  • @muthukrishnan597
    @muthukrishnan5979 ай бұрын

    You are a good mentor❤

  • @tejeswararaobudumuru9206
    @tejeswararaobudumuru9206 Жыл бұрын

    Hi Gautham, The session was a nice refreshment. Thank you..

  • @turnover1618
    @turnover16185 ай бұрын

    Q5. The written question is explicitly asking to present the project status - so answer is the performance reports. The question is not 'how' to present the status or 'which document describes how to present it' , as you mentioned verbally and picked up the CMP answer ....

  • @user-qw6wo6bs1j
    @user-qw6wo6bs1j Жыл бұрын

    Hi Gautham!

  • @umamaheswariannadurai8462
    @umamaheswariannadurai84623 ай бұрын

    TanQ

  • @naveengs1417
    @naveengs14177 ай бұрын

    Hi Gautham For the last question, thanks for the explanation, am understood that its CMC...but question asked which document...so i thought Communication management plan is not document but plan..so i selected WPR...thanks..i got confused seeing document word but your explanation helped😊

  • @nizarworld2020
    @nizarworld202010 күн бұрын

    Q3 why didn't update risk register? as its the first step then go for change process right ?, then plan update . isn't it ?. I think its a risk. also mention it may affect so future its could leads to problem

  • @pradeepavaidee7912
    @pradeepavaidee791211 ай бұрын

    HI Gautam, I agree the first step is to update the issue log, but how does this solve the purpose or provide solution?They have asked how to handle the situation since it needs to be fixed in 2 days.

  • @knowledge_is_power1375
    @knowledge_is_power137510 ай бұрын

    I really appreciate the PMI decision since what I personally feel there are many proxy candidate who diluting PMP standard.

  • @turnover1618
    @turnover16185 ай бұрын

    Q4. You referred to CCB, though the approach is Hybrid ?

  • @shubhamjain2312
    @shubhamjain231210 ай бұрын

    I am little confused. Ques 1 and 4 are very similar. In q1, you asked to choose what will you do first but in ques 4 you chose the option to follow the change control process.