How to do Line balancing in product Layouts
In this video , you will learn how to do line balancing for layouts.
Line balancing is used to assign individual tasks to workstations for a desired output rate.
Idle time and the number of workstations are minimized.
Steps followed in line balancing:
1. Draw Precedence diagram
2. Calculate cycle time
3. Theoretical number of workstations
4.Workstation Assignments
5. Efficiency
#linebalancing #productlayouts #cycletime #takttime #efficiency.
00:00 Intro
01:01 Precedence Diagram
03:00 Cycle time
04:02 Theoretical Number of Workstation
05:17 Assign Workstation
10:57 Efficiency
Keep Watching,Keep Learning
Пікірлер: 99
Thanks for watching the videos. The chapters are added for your reference 00:00 Intro 01:01 Precedence Diagram 03:00 Cycle time 04:02 Theoretical Number of Workstation 05:17 Assign Workstation 10:57 Efficiency
@sunitapathak9055
Жыл бұрын
z
Perfectly explained & thanks for providing the reference books for further research & study based on their production process complexity tasks.
Thank you for the explanation! I have a project about production layouts and my teacher didn't really explain how to use line balancing, but you did!
Absolutely amazing. Clear and precisely explained. Thank you.
Saved a life here. So grateful.
Best!
Very very nice Lecture Ma'am, I follow your teaching when I hv to know the clear concept
Crisp and clear mam. Keep uploading.
Very clear presentation
Awesome video. Thank you
Wow so great, very easily understand
Finally I got the solution to these sum 🙌 Thank u so much 💓
You saved my day. This video was very helpful for my assignment.
Thank you !! Your the best !
Excellent explanation, generally Indian are awesome in explaining
I have gone through many videos , none of them have understood. This video is cleared all my doubts . Thank you so much maam. God bless you.
@karpagamqtcorner8764
2 жыл бұрын
Most welcome 😊
amazing explanation
Thanx... Good affect
Very nicely explained.....
thank you so much madam..pls keep making such videos
Great!! Nice explanation. Thanks Karpagam mam 😊
@karpagamqtcorner8764
5 ай бұрын
Most welcome sir.
Thank you ma’am your video was actually very nice
Thanks a lot mam 🙏🙏🙏 Great explanation I understood all the things at once without any doubts.
@pushpendraatre1412
2 жыл бұрын
Mam please also upload the videos for Johnson Rule ,Time series methods of forecasting, facility planning methods such as factory rating ,weight score method,Load distance method and also Centre of gravity.It will be great help for the students like me.
My professor is useless. Thank you so much Karpagam! You really made this easy to learn
Thank you so much ma'am ❤
Thank you 😍✌️
thank you so much ma'am.
Thank you so much ma'am. Now i will get 10 marks bcz of this. Awesome
@karpagamqtcorner8764
2 жыл бұрын
Most welcome 😊
Perfect description
@karpagamqtcorner8764
2 жыл бұрын
Glad you liked the video
Thanku 🥰
thanks a lot mam,very clear and informative
@karpagamqtcorner8764
2 жыл бұрын
Thanks for liking and Keep Watching
What an amazing video that I have ever seen on the youtube..Keep uploading more so that Yu can help same fellow students like me.. Thumbs up!!!
@karpagamqtcorner8764
2 жыл бұрын
Stay tuned for more such videos
thank you so much
Nice fluent explanation .
@karpagamqtcorner8764
2 жыл бұрын
Thanks for liking suresh chandra
Hi Mam I would like to know if is possible to compute lower bound on required no of workstations
from 2023, thank you, ma'am.
Smart. Brilliant. Clear. Thank you. You have one on inventory management?
@karpagamqtcorner8764
2 жыл бұрын
Thanks Kabugo Kusain. Please mention the topic that you need. Will share the videos and share it across.
Good presentation. How to improve the efficiency of the line balancing ?. When it will reach 100 %
Thank you so much
@karpagamqtcorner8764
2 жыл бұрын
You're most welcome Gyaneshwar Goud
thank you ma'am
thank you so much maam
How to calculate smoothness index for above problem?
Thank you so much mam 💟
@karpagamqtcorner8764
2 жыл бұрын
Most welcome 😊Mohammed Ubaid Shaikh
Hi Karpagam! Thank you very much for the explanations! :) Could you recommend some books to read on Line Balancing and Kanban, please? Thank you! :)
@karpagamqtcorner8764
2 жыл бұрын
Hi MM, I follow these books for Kanban and assembly line 1. Kanban made simple - John M Gross and Kenneth R Mcinnis 2. Kanban controlled manufacturing systems- George Krieg 3. Assembly Line Balance- Thomas Shropshire 4. Assembly Line Balance - Waldemar Grzechca I'm glad that you enjoyed the video.
beautiful voice ma'am
Thank you
@karpagamqtcorner8764
2 жыл бұрын
You're welcome
Nice one mam, if line effeciency is 73% then OEE will much less than 73% am I correct?
@karpagamqtcorner8764
2 жыл бұрын
Yes Sir, you are right. OEE will be less than the line efficiency
Thank you ma'am
@karpagamqtcorner8764
2 жыл бұрын
Thank you too for watching this video and liking it
Isn’t takt time different from cycle time? So do we need to take takt time or cycle time in the formula?
@karpagamqtcorner8764
2 жыл бұрын
Takt time and cycle time are different. Cycle time is the average time taken to complete the activity whereas takt time refers to the time between the start time of the one activity and subsequent activity. We have to consider cycle time only
Super woman 🔥🔥🔥🔥🔥
If 4 is the actual workstation how to calculate.
I have undersood this method mam tnq...but i need line balancing layout with followers method
@karpagamqtcorner8764
2 жыл бұрын
Sure Imran. I will make a video and share the link with you shortly.
@imranplay4568
2 жыл бұрын
@@karpagamqtcorner8764 ok mam thank you
Nice video
@karpagamqtcorner8764
2 жыл бұрын
Thanks
@chauhanajay7744
2 жыл бұрын
In the last minute if exam I saw your video it is really crisp and clear
@karpagamqtcorner8764
2 жыл бұрын
That's great to hear Chauhan Ajay. Wish you all the best for your exams
How to find out the length of critical path mam
Bettter explaination than my proffesor Kirit at a premier B-school
@user-zp1jx3ef4r
4 ай бұрын
kirit ghosh nmims
How to assign when no of followers and task time both are same?
I thought the actual cycle time will be 2 rather...why did you use 2.4 when calculating the efficiency
Hello Mam, if the available time is 8 hours equal 480 min. and the sum. of time is 8.75 min. its mean that the Deli company only can make around 54 pizza in 8 hours. How they can fulfill the demand which is 200 pizza in 8 hours?
Ma'am, isn't takt time different with cycle time, is it?
Cycle time is 2 in actual and 2.4 is theorethical. So can we say what you found at the end as efficiency is theorethical not actual efficiency? Otherwise instead of 2.4, 2 should be used...
73% efficiency is after we balance the line?? kindly let me know what balancing is done here, the tasks are same in sequence
Thank you madam but I did not understand the last part
WHy we are not doing D and E Seperately in task order??
@karpagamqtcorner8764
2 жыл бұрын
D and E are burst activity. The activity which has the longest time will be given the preference
why did it turn out to be 5 stations and not 6, cause cycle time is 2.4, activity F is 1.5, and activity G is 0.5, which is 2.5 and more than 2.4, which should not be. please explain
@karpagamqtcorner8764
2 жыл бұрын
Activity F and activity G turns out to be only 2 minutes, whereas the available time is more than 2 mins. Because of the cushion in total time, it is accommodated in station 5
dont get it the last part
11:56 how to find out the length of the critical path
Two type of Product is out put
Bhaq samajh me nahi aaya ! How to assign no of element in diffrent w.s
The photo is not readable
Process is Clear but not Concept (After C Parallel Process than F& G Series
Baids gather 😂😂😂😂😂😂😂😂
Very clear presentation
@karpagamqtcorner8764
2 жыл бұрын
Glad you think so!