Factory Acceptance Test Explained - Part 1 | Power the Control Panel

▶ C'mon over to realpars.com where you can learn PLC programming faster and easier than you ever thought possible!
=============================
▶ Check out the full blog post over at
realpars.com/factory-acceptan...
=============================
⌚Timestamps:
00:00 - Intro
00:35 - Acceptance Test
01:56 - FAT example
02:52 - Step 1) Power the control panel
03:46 - Point #1
04:23 - Point #2
04:38 - Step 2) Switch on all the devices in the control panel
=============================
In the world of industrial automation, a Factory Acceptance Test or FAT is simply a test for a newly manufactured control system that takes place at your factory or your workshop before you ship the control panel to the customer.
With a Factory Acceptance Test, you make sure that everything works properly before you deliver a control cabinet to a customer.
Let’s explore FAT a bit further through a practical example.
Let’s say that you are a company that designs and implements industrial control systems. These control systems often come in the form of a control panel built into a control cabinet.
You’ve built the control panel and now it’s ready to ship to the customer. But before you ship it you want to make sure that everything works properly. The last thing you want is to ship it to the customer’s site only to find out that things are not quite working the way they should.
Consequently, you will have to spend countless hours at the client’s site solving issues that you could have easily taken care of before shipping the control panel. So, as the name suggests, a FAT is completed at the factory.
Now you may be wondering, where should I start? What do I need to test? Well, I will show exactly that through a step-by-step example.
Step 1
As the first step, you need to connect the power to your control cabinet and turn it on. We have a main circuit breaker for every control panel. This is where the power comes into the control panel for all of the devices.
To let the electricity come into the panel, you need to connect the power to the topside of the circuit breaker. This is a wire that comes from outside of the panel.
You connect it to the circuit breaker only for testing and once you are done and want to ship the cabinet, you simply disconnect the wires from the topside of the circuit breaker.
The power that comes into the panel can be anywhere from 480 volts AC to as low as 120 volts AC depending on where you are and the country you are based in.
Once you have the power connected to the topside of the circuit breaker, you can switch it on for the power to flow to the control panel.
Although this seems a very simple process so far, there are two important points that you need to consider when trying to power on your control panel:
#1
The circuit breaker generally has a disconnect on the outside of the panel that allows you to shut off the power. Before you want to connect the cable to the main circuit breaker inside the panel make sure that you have disconnected the power using this switch.
Don’t take the hot power into your hand and try to connect it to the circuit breaker. This is dangerous.
#2
The second point to consider here is that when you switch off the circuit breaker, the topside of it will still have power. So, again, before you want to disconnect the power you need to make sure that you have disconnected the power from the outside of the panel.
Step 2
Now that you have connected the power cable to the control panel and switched on the circuit breaker, you also need to switch on any other breakers or fuses that you may have on the way to power the PLC and the other devices.
In the end, I also switch on the PLC power supply as well. The PLC power supply could be installed on the same rack as the PLC or somewhere else on the panel. We may have one, two, or three power supplies on our panel depending on how many devices we need to power on in the control panel. The more devices we have, the more power we need to turn them on.
=============================
Missed our most recent videos? Watch them here:
realpars.com/phoenix-contact-...
realpars.com/boolean-logic
realpars.com/plcnext-engineer
=============================
To stay up to date with our last videos, make sure to subscribe to this KZread channel:
bit.ly/realpars
=============================
TWEET THIS VIDEO ctt.ac/c9UiH
=============================
Follow us on Facebook: / therealpars
Follow us on Twitter: / realpars
Follow us on LinkedIn / realpars
Follow us on Instagram / realparsdotcom
#RealPars #FAT #Control_Panel

Пікірлер: 69

  • @saurabhbhardwaj9667
    @saurabhbhardwaj96673 жыл бұрын

    Control system FAT usually comprises of Hardware and Software FAT. Before starting with FAT, it is important that all the documents required for performing FAT are available: system configuration, P&IDs, I/O list, Functional design specifications, HMI design specification, Alarm and trip setting list, Logic diagrams, Control loop diagrams, HMI screen, Specification of Control system hardware, panel GAD and wiring diagram, Bill of material, list of signal exchange with third party interface ( hardwired and soft signals) and FAT procedure as a minimum. All these documents should be approved by your customer before you can take a panel into manufacturing and start with system development. A FAT procedure lists the detailed procedure for testing of hardware, I/Os, program, HMI interface and third party interface as much as practicable.

  • @realpars

    @realpars

    3 жыл бұрын

    Saurabh, thank you for the extended explanation of many of the components (hardware, software, documentation, drawings, etc.) that are included in the FAT process. Your comments will certainly help our viewers to better understand the scope of the FAT test!

  • @saurabhbhardwaj9667

    @saurabhbhardwaj9667

    3 жыл бұрын

    RealPars Team, you are most welcome. Understanding the documentation requirement and the purpose of each type of document at each stage of FAT is a pre-requisite to a successful FAT. In my experience, I have seen that FAT procedures are not so well written by control system vendors and end up widening a gap between one's expectations and what is offered by the vendor. Hope my feedback serves as a value addition to your team responsible for developing content for KZread channel.

  • @prabhakaran20ten

    @prabhakaran20ten

    2 жыл бұрын

    @@realpars Great❤️

  • @JC-xc8rx

    @JC-xc8rx

    Жыл бұрын

    @@saurabhbhardwaj9667 thank you so much for sharing your knowledge and experience. Much respect.

  • @emmanuelsanusi1389
    @emmanuelsanusi13893 жыл бұрын

    Thank you Realpars team!!

  • @realpars

    @realpars

    3 жыл бұрын

    Our pleasure, Emmanuel!

  • @behroozma9946
    @behroozma99462 жыл бұрын

    Thank you Realpars team🙏

  • @realpars

    @realpars

    2 жыл бұрын

    You're very welcome, Behrooz!

  • @jagdeepminhas7669
    @jagdeepminhas76693 жыл бұрын

    Valuable for me to level up my knowledge

  • @muzammilsyed6225
    @muzammilsyed62253 жыл бұрын

    Very basic but very important. Wonderfully explained. Thx

  • @realpars

    @realpars

    3 жыл бұрын

    Glad it was helpful!

  • @CommercialGasEngineerVideos
    @CommercialGasEngineerVideos Жыл бұрын

    These vids are helpful as there aren't many in the UK. Thanks

  • @realpars

    @realpars

    Жыл бұрын

    Glad you like them!

  • @bitebonumbere1426
    @bitebonumbere14263 жыл бұрын

    Thank you RealPars

  • @realpars

    @realpars

    3 жыл бұрын

    Our pleasure, Bitebo! Happy learning.

  • @aminokamad1681
    @aminokamad16813 жыл бұрын

    Can't wait part 2 video

  • @realpars

    @realpars

    3 жыл бұрын

    Glad to hear your anticipation, Amin!

  • @MohamedSoliman-rm6mt
    @MohamedSoliman-rm6mt3 жыл бұрын

    Very Valuable Information Thank you, RealPars

  • @realpars

    @realpars

    3 жыл бұрын

    Glad it was helpful, Mohamed!

  • @alexandernorman5337
    @alexandernorman53373 жыл бұрын

    In my experience, the secret to a good FAT is to identify and test all functionality. It's usually not possible to reproduce all the inputs, outputs, and interfaces of the destination plant. But identify every type and test a representative sample, and scale your system so that it can handle the full requirement.

  • @realpars

    @realpars

    3 жыл бұрын

    Alexander, this is a great observation! In small FAT tests of a single panel, it may practical to test every point and I/O terminal. However, in very large systems, a representative sample, perhaps one point from every I/O card, or verification of power at the "endpoints" per the panel drawings, will give a high probability of suitability for installation in the field. Again, the client has the final say in the scope of the FAT, since they are "footing the bill" for the time it takes to complete the testing.

  • @adekolasulaiman2549
    @adekolasulaiman25493 жыл бұрын

    Nice and good job. Thanks for sharing.

  • @realpars

    @realpars

    3 жыл бұрын

    Our pleasure, happy learning!

  • @mufti1312
    @mufti13123 жыл бұрын

    I have started my career in automation last year.. Your every presentation is very useful.

  • @realpars

    @realpars

    3 жыл бұрын

    Glad to hear that! Best of luck!

  • @godtermand
    @godtermand3 жыл бұрын

    In developing a new plant, we also use the FAT to test SCADA checking TAGs, units, scalings, texts, alarm areas etc. We also let the operators get a hands on experience by navigating in a safe environment and let them give their inputs before the functionality and software is locked for site testing.

  • @realpars

    @realpars

    3 жыл бұрын

    Thanks for sharing your experience with us!

  • @marlonzapata8240
    @marlonzapata82403 жыл бұрын

    It's an important video, i like to learn by watching all your videos. A step that i used to do before turn on the main braker is to check with the multimeter with continuity, the possibles shorts circuits between lines that helps tolo correct the conections and saves the elementd of the control panel.

  • @realpars

    @realpars

    3 жыл бұрын

    Thanks for your kind support, Marlon!

  • @navnitpatel8487
    @navnitpatel84873 жыл бұрын

    Nice. Would like to see more videos .

  • @realpars

    @realpars

    3 жыл бұрын

    More to come!

  • @preetamsagarsahu
    @preetamsagarsahu3 жыл бұрын

    Thanks for introducing FAT to me

  • @realpars

    @realpars

    3 жыл бұрын

    Our pleasure, Preetam!

  • @dharunnarayanankasi2564
    @dharunnarayanankasi25643 жыл бұрын

    Very useful 👍

  • @realpars

    @realpars

    3 жыл бұрын

    Thanks a lot!

  • @odeaore1316
    @odeaore13163 жыл бұрын

    I have already done this kind of task for automotive industry in France, and they asked to check the tension too, and in the end you must sign.

  • @paulrinehart5557
    @paulrinehart55573 жыл бұрын

    I would like to see a video on incorporating a battery backup into the PLC. Nice job on the FAT.

  • @realpars

    @realpars

    3 жыл бұрын

    Hi Paul! Thanks for your comment and your suggestion. I will pass this on to our course developers! Thanks for sharing and happy learning!

  • @aminokamad1681
    @aminokamad16813 жыл бұрын

    Awesome video 🔥 🔥 🔥

  • @realpars

    @realpars

    3 жыл бұрын

    Thank you, Amin!

  • @hamzamohamed7935
    @hamzamohamed79353 жыл бұрын

    I like this vedio because i found it sooo useful

  • @realpars

    @realpars

    3 жыл бұрын

    That's great to hear, Hamza!

  • @ghanshamshirbhate1034
    @ghanshamshirbhate1034Ай бұрын

    thanks.....Explained Very Nicely.....Really Helpful...…..Keep it up...…Waiting for the Video on SAT (Site Acceptance Test)

  • @realpars

    @realpars

    Ай бұрын

    Happy to hear that!

  • @karimsh4281
    @karimsh42813 жыл бұрын

    Nice one. would you kindly make a vedio about PLC software based PC

  • @realpars

    @realpars

    3 жыл бұрын

    Hi Karim! Thanks for your comment and your suggestion. I will pass this on to our course developers! Thanks for sharing and happy learning!

  • @judetochukwuogbozor6355
    @judetochukwuogbozor63553 жыл бұрын

    Wonderfully explained. #first_to_comment

  • @realpars

    @realpars

    3 жыл бұрын

    Thanks for your support!

  • @TheSikandarNawaz
    @TheSikandarNawaz3 жыл бұрын

    I believe first step is to check the integrity of wiring and if proper grounding is in place. I have had bad experience of wrong wiring where short circuit happened just after panel is powered on. Also in one instance the grounding was not properly fixed and one of the PLC card burnt because of electrostatic discharge.

  • @realpars

    @realpars

    3 жыл бұрын

    Thanks for adding that, Sikandar!

  • @nallamanish155
    @nallamanish1553 жыл бұрын

    Hello Realpars. If it's possible kindly make a video for ground bond test. Insulation resistance test. HV test, Megger test, Earthing leakage relay test. Thank you.

  • @realpars

    @realpars

    3 жыл бұрын

    Hi Nalla! Thanks for your comment and your suggestion. I will pass this on to our course developers! Thanks for sharing and happy learning!

  • @basilrasool
    @basilrasool3 жыл бұрын

    very good

  • @realpars

    @realpars

    3 жыл бұрын

    Thank you!

  • @KevIn-tu4fv
    @KevIn-tu4fv3 жыл бұрын

    Make sure to do a point-to-point test before turning on the main power. Somestimes the connections made during the building of the panel can be wrong.

  • @realpars

    @realpars

    3 жыл бұрын

    Thank you, Kevin!

  • @mizanurrahman-jk1gy
    @mizanurrahman-jk1gy3 жыл бұрын

    Nice

  • @SandeepKumar-ng2bq
    @SandeepKumar-ng2bq3 жыл бұрын

    Nice 👍👍👍👍👍👍👍👍

  • @realpars

    @realpars

    3 жыл бұрын

    Thank you!

  • @Anil.Varanasi
    @Anil.Varanasi2 жыл бұрын

    Hai, What is Configuration Acceptance Test for PLC?

  • @realpars

    @realpars

    2 жыл бұрын

    SA Configuration Acceptance Test for a PLC is a systematic test and/or verification that the configurable parameters in the PLC (IP address, port baud rates, connected device node numbers, etc., meet the values contained in the hardware or configuration specification document.

  • @tamilselvans7117
    @tamilselvans7117 Жыл бұрын

    Hi can anyone tell me how to check pull test (any device available) of the the Connected wire in Terminal block , MCB, PSU, ,,,

  • @realpars

    @realpars

    Жыл бұрын

    If I understand your question correctly, you want to verify that the wires are securely terminated. The "pull test" is actually a very good test to perform, since many times, a panel builder will not tighten the wires per spec. To do a pull test, make sure the power is disconnected from the panel. Then gently tug each wire (small amount force) to see if the wire comes loose from the terminal. If so, reinsert and tighten. If wires do not make good solid contact with the terminals, they could arc, or simply not make contact such that the device wiring prevents proper operation.

  • @tamilselvans7117

    @tamilselvans7117

    Жыл бұрын

    @@realpars yeah thanks for the info.i am asking about any device or instruments are there to check pull test.with the equipment not with hands.

  • @mehulpatel9579
    @mehulpatel95792 жыл бұрын

    👍🏻

  • @ominence5573
    @ominence55733 жыл бұрын

    Full point to point wire test should be at least undertaken before power up, this will minimize short circuit faults etc.

  • @ahmednor5806
    @ahmednor58062 жыл бұрын

    🙏🌹🌹