Phase 2B - Airport to Hebbal
***********************************************
JUNE 2024 Updates
Civil Contractor : PKG2 - NCC LTD - 11.678 KM
PKG3 - NCC LTD - 15.011 KM including 718 meter cut and cover portion.
Piling Works Happening and Pier casting Picking up pace.
Package 2 :
Kodigehalli Station :- RHS Pier casting in Progress. LHS Piling completed.
Jakkur Cross Station :- CC Beam casting to begin
Jakkur Plantation Station : Unsure
Yelahanka / Kogilu Cross Station :- Concourse beam casting in progress
Bagalur Cross Station : U girder Done. Concourse i-girders done. Platform i-giders in progress
Package 3 :
Bettahalasuru Station : Unsure
Chikkajala Station : Pier casting is in progress
Doddajala Station : Beam casting for Concourse level has begun
Stations done by KIAL :
Airport City Metro Station : Tenders for Civil works to be awarded.
Airport Terminal Metro Station : Civil works complete. Finishing works pending
ಬಿಎಂಆರ್‌ಸಿಎಲ್ | ಕೆ.ಆರ್‌.ಪುರ ನಿಂದ ಕೆಂಪೇಗೌಡ ಅಂತರ್ ರಾಷ್ಟ್ರೀಯ ವಿಮಾನ ನಿಲ್ದಾಣ | ಏರ್ಪೋರ್ಟ್ ಮೆಟ್ರೊ ಎರಡನೇ ಹಂತ-2B
------------------------------
Track: Joy - Next Route [Audio Library Release]
Music provided by Audio Library Plus
Watch: • Joy - Next Route | Fre...
Free Download / Stream: alplus.io/joy
------------------------------

Пікірлер: 57

  • @skb064
    @skb064

    Bro like this only please do Pink Line elevated stations also bro

  • @wasi8048
    @wasi804821 күн бұрын

    Why are the tracks not elevated inside airport area? Is it because of upcoming taxiway that will connect both runways?

  • @IndianGeek5589
    @IndianGeek558914 күн бұрын

    No pic of KIAL terminal or Airport City Metro station?

  • @shreyass5664
    @shreyass5664

    Hi sir what is the differences between normal pier caps and excentric pier caps

  • @SulekhaDhar-pj6xz
    @SulekhaDhar-pj6xz2 сағат бұрын

    Waiting for your updates

  • @shreyass5664
    @shreyass56649 сағат бұрын

    Hi sir waiting for your july month metro videos😊

  • @siddhartharoy8834
    @siddhartharoy8834

    So thankful, major concern regarding the development at IAF Yelahanka. Will it go underground or at level?

  • @mdshariq7218
    @mdshariq7218

    Your channel is so underrated

  • @tejass4657
    @tejass4657

    Tejas.s bjp

  • @prasadanand1252
    @prasadanand1252

    Can it be expected to be completed by December 2027?😊

  • @ArnavA-un5gk
    @ArnavA-un5gk

    most considtent updater for namma metro

  • @bhuvankumar7611
    @bhuvankumar761121 сағат бұрын

    Waiting for blue and yellow line

  • @pradeepdnm
    @pradeepdnm28 күн бұрын

    Hey,

  • @shreyass5664
    @shreyass5664

    Thanks for uploading june month video 😊👍

  • @AbHi-tm5dh
    @AbHi-tm5dh

    You are doing a wonderful job ❤️❤️❤️

  • @vijaysrini27
    @vijaysrini27

    26:02

  • @alrahmanfurniture5329
    @alrahmanfurniture532921 күн бұрын

  • @JoeyJordanson
    @JoeyJordanson

    Thanks for the video! Do you hae a general Idea when all the stations could have their U girders and platform i girders ready or are they planning on fiinishing one station first and moving on to the other after completion

  • @suyashkd
    @suyashkd

    Good job! One suggestion, you can try uploading the video in 2x speed as it still will be equally useful but at half the video length

  • @vijethkumar6549
    @vijethkumar6549

    For Jakkur Plantation station have they kept space for building the station,.?

Келесі