Work Performance Data, Information, & Report: Master the Differences in 10 Minutes for your PMP Exam

If you ask PMP aspirants to choose one concept that’s confusing, I am sure most of them will choose the difference between WPD, WPI and WPR as one of the concepts. In this video, our lead trainer and Project Management Mentor Gautham Sudakar dives deep into the world of work performance data (WPD), work performance information (WPI), and work performance reports (WPR).
Learn the key differences between these concepts and how they impact project management.
We'll walk you through a practical example, showcasing how data is collected, transformed into information, and finally presented in a report to stakeholders. This step-by-step process will help you better understand how to effectively manage and communicate project progress.
📝 Timestamps:
🕒 00:00 - Introduction
🕒 01:18 - Work Performance Data (WPD) Explained - Work Performance Data (WPD) is the raw data collected from various project areas, such as planned and actual performance, budget, and status.
 Data collection is crucial for effective project management.
 Examples include: hours worked, tasks completed, and resources used.
Practical Example -Gautham walks through a detailed, real-life example to demonstrate the transition from WPD to WPI and finally to WPR. This example helps viewers visualize how these concepts apply to real projects and the importance of each step in the process.
🕒 05:25 - Work Performance Information (WPI) Explained - Work Performance Information (WPI) is the result of analyzing and comparing the collected work performance data.
 This step involves identifying variances, trends, and potential issues in the project.
 Examples include: schedule variance, cost variance, and overall project progress.
🕒 07:35 - Work Performance Reports (WPR) Explained - Work Performance Reports (WPR) are the presentations or documents that contain work performance information, formatted for easy consumption by stakeholders.
 This is the final step in effectively communicating project performance.
 Examples include: project status reports, project dashboards, and variance analysis reports.
🕒 08:23 - Interactive Test -The test at the end of the video allows viewers to apply their knowledge of WPD, WPI, and WPR. Here is a list of items as promised in the video
 Number of defects found.
 Finish dates of activities
 Deliverable status.
 Number of change request completed.
 Implementation status of change request.
 Status reports representing implementation status of change request.
 Electronic dashboard representing deliverable status.
Please segregate these items in WPD, WPI, and WPR and make sure you give your reasoning behind the answer in comments section below, where Gautham will personally respond to submissions.
🕒 9:02 - Conclusion
Don't miss the test at the end of the video! This interactive challenge will help you validate your understanding of these concepts. Grab your notepad, and let's get started! Be sure to leave your answers in the comments section, and Gautham will personally respond to your submissions.
Join us on this educational journey, and solve your work performance data, information, and report related PMP Questions easily! Happy learning, and don't forget to like, share, and subscribe the EduHubspot Channel for more project management insights!
For any queries, reach out to Gautham at Gautham.sudakar@eduhubspot.com
Connect with me on LinkedIn directly : / gautham-sudakar-pmp%c2...
Visit our website www.eduhubspot.com today and discover how the PMP Mindset tool can help you achieve greater success in your career!
Do check out our PMI Approved PMP Program at:
www.eduhubspot.com/packages/pmp
Also, you can email our support team for more questions at services@eduhubspot.com
Connect with us on WhatsApp: wa.me/message/XVI7DMTEACX7L1
Subscribe to our KZread Channel: goo.gl/2ZjpEq

Пікірлер: 162

  • @manishashetty7965
    @manishashetty796514 сағат бұрын

    Thank you Gautam, WPD - Raw Data collecting plan & actual progress  Number of defects found. = WPD  Finish dates of activities = WPD  Implementation status of change request = WPD WPI Comparing plan and Actual progress  Deliverable status. = WPI  Number of change request completed. = WPI WPI gathered and presented through Electronic Representation - WPR  Status reports representing implementation status of change request = WPR  Electronic dashboard representing deliverable status= WPR

  • @sharmilapratap343
    @sharmilapratap3432 сағат бұрын

    Thank you Gautam for making it so simple and easy. So for me:  Number of defects found = WPD as it will be just actual data of defects  Finish dates of activities = Again WPD, where later we can use this information for comparison.  Deliverable status. = WPI as it gives project status  Number of change request completed. = WPD  Implementation status of change request.= WPI as we can compare  Status reports representing implementation status of change request. WPR = Presentation of status report  Electronic dashboard representing deliverable status. WPR = Electronic representation

  • @SaurabhGupta-fl1vp
    @SaurabhGupta-fl1vp3 ай бұрын

    Great Explanation:  Number of defects found. -- WPD -- Raw data  Finish dates of activities -- WPD -- Raw data  Deliverable status. -- WPI -- compared status  Number of change request completed. -- WPD -- Raw data  Implementation status of change request. -- WPI -- compared status  Status reports representing implementation status of change request. -- WPR -- Report  Electronic dashboard representing deliverable status. -- WPR -- Report

  • @EduHubSpot

    @EduHubSpot

    2 ай бұрын

    Very Impressive !! Gautham

  • @tejeswararaobudumuru9206
    @tejeswararaobudumuru9206 Жыл бұрын

    Hi Gautham, Item-1: WPD. It's just actual data and there will never be planned defects to compare the actual defects. Item-2: WPD. It's just finish dates of activities . If we compare actual finish dates with planned finish dates, we can know the project status. Item-3: WPI. It provides the project status. Item-4: WPD. It's just data. It won't provide the project status. Item-5: WPI: It derives from planned vs actual and can provide the project status Item-6 &7: WPR: They are representations of project status

  • @EduHubSpot

    @EduHubSpot

    Жыл бұрын

    Really loved your thought process. I need to steal this reasoning. Hahah !! Gautham

  • @jpsinghditp

    @jpsinghditp

    Ай бұрын

    @@EduHubSpot @tejeswararaobudumuru9206 Awesome explaination

  • @SubhankarDey-mr9um
    @SubhankarDey-mr9um2 ай бұрын

    You have made it so easy. thanks Gautam.

  • @EduHubSpot

    @EduHubSpot

    2 ай бұрын

    Thanks for liking ! Gautham

  • @pavanrudraraju7048
    @pavanrudraraju704825 күн бұрын

    Very informative. Great explanation! Thank you

  • @EduHubSpot

    @EduHubSpot

    21 күн бұрын

    Glad you enjoyed it! Gautham

  • @nehapashiney4045
    @nehapashiney4045Ай бұрын

    Perfectly explained.... @Gautham.....Thank you  Number of defects found - WPD  Finish dates of activities - WPD  Deliverable status - WPI  Number of change request completed - WPD  Implementation status of change request - WPI  Status reports representing implementation status of change request - WPR  Electronic dashboard representing deliverable status - WPR

  • @EduHubSpot

    @EduHubSpot

    Ай бұрын

    That is exactly how you should think. Gautham

  • @priyankaali06
    @priyankaali0610 ай бұрын

    Thanks a lot gautam for this

  • @EduHubSpot

    @EduHubSpot

    10 ай бұрын

    I am glad you loved my video. Gautham

  • @pushpafire2715
    @pushpafire2715 Жыл бұрын

    Thank you gautham...

  • @EduHubSpot

    @EduHubSpot

    Жыл бұрын

    Your Most Welcome Satish !! Gautham

  • @crispingeorge2502
    @crispingeorge2502 Жыл бұрын

    Hi Gautham, Grateful for taking your time to explain this concept. Q(1,2 &4) refer to work performance data; since they are talking about raw observations/measurements. Q(3&5) refer to work performance information; status of WPD being performed. Q(6&7) refer to work performance report; physical or electronic representation of WPI. Regards

  • @EduHubSpot

    @EduHubSpot

    Жыл бұрын

    Loving your thought process. Gautham

  • @krishnar.p1966
    @krishnar.p19667 ай бұрын

    Hi Gautham, It is very interesting to listen to your videos and iassume it will stay in our mind forever. Thanks. WPD - collecting on plan and execution, it should be raw observation (1,2,4) WPI - it is comparing and finding actual progress, it should be some status, here deliverable and implementatation "status" (3, 5) WPR - It is a representation of the WPI, here representation of "deliverable and implementatation "status"" (6,7)

  • @EduHubSpot

    @EduHubSpot

    7 ай бұрын

    Loving your thought process. Gautham

  • @mohitmhatre5021
    @mohitmhatre50215 ай бұрын

    Excellent!

  • @EduHubSpot

    @EduHubSpot

    5 ай бұрын

    Glad you liked it! Gautham

  • @sameershaikh-km3xr
    @sameershaikh-km3xr4 ай бұрын

    Very Good Explained with Examples!!! 1,2,4 is WPD. And 3,5 is WPI and 6,7 are WPR

  • @EduHubSpot

    @EduHubSpot

    4 ай бұрын

    Very impressive!! Gautham

  • @user-nt8ww1mu2q
    @user-nt8ww1mu2q Жыл бұрын

    Hi, Gautham, concept was explained very well, and you rocked as always with your real-life example explanation. thanks  A number of defects were found. -WPD  Finish dates of activities -WPD  Deliverable status. -WPI  A number of change requests were completed. -WPD  Implementation status of a change request. -WPI  Status reports represent the implementation status of change requests. -WPR  Electronic dashboard representing deliverable status. -WPR

  • @EduHubSpot

    @EduHubSpot

    Жыл бұрын

    Thanks Vasundhara for lovely comment. 7 out of 7, very impressive !! Gautham

  • @Theresa-wr8hc
    @Theresa-wr8hc Жыл бұрын

    Hi Gautham, I really loved the explanation. thanks #defects -WPD Finish dates - WPD Delivery status - WPI #change request - WPD Implem status - WPI Status rpt rep imple status - WPR Electronic Dash - WPR

  • @EduHubSpot

    @EduHubSpot

    Жыл бұрын

    Glad you liked it, Theresa. Your answers are correct!. Great job Gautham

  • @kafilahmad
    @kafilahmad8 ай бұрын

    Thank you

  • @EduHubSpot

    @EduHubSpot

    7 ай бұрын

    You're welcome !! Gautham

  • @ruwanthiharshanie7761
    @ruwanthiharshanie7761 Жыл бұрын

    Hi Gautham, Work Performance Data: These are row data which can be used for decision making; 1. Number of defects found, (This can be compared with estimated number of defects to come up with useful WPI) 2. finish dates of activities, ( This can be compared with planned finish dates of activities to come up with useful WPI) 4. Number of change requests completed ( This can be compared with number of change requests planned to complete, to come up with useful WPI) Work Performance Information: These are found after processing the data; comparing planned and actual data 3. Deliverable Status, (whether the delivery is complete or delayed or whatever the current status can only be determined with comparing the planned and actual progress data) 5. Implementation Status ( this also can be determined with comparing planned and actual progress data) Work Performance Reports:This is the presentable format of the information on status 6. Status reports representing implementation status of change request, 7. Electronic dashboard representing deliverable status

  • @EduHubSpot

    @EduHubSpot

    Жыл бұрын

    Really loved your thought process. I need to steal this reasoning. Hahah !! Gautham

  • @mailtoaravindan
    @mailtoaravindan5 ай бұрын

    Hi Gautham, As always, great explanation... My answers below... WPD - 1,2,4 (All three involves collecting raw data) WPI - 3,5 (Status update is Information) WPR - 6,7 (Representing the status is report)

  • @EduHubSpot

    @EduHubSpot

    5 ай бұрын

    Very Impressive !! Gautham

  • @gajasen
    @gajasen11 ай бұрын

    @Gautham I loved the way you explained this concept. It would stay fresh in my mind. Work Performance Data : Number of defects found, finish dates of activities, as these are the raw information. Work Performance Information - Deliverable Status, No. of change request completed Implementation status of change request This information is derived by comparing the actual vs planned and hence it helps in arriving at the status of the project. Work Performance Report : Status reports representing implementation status of change request. Electronic dashboard representing deliverable status. These are the electronic representation of the information for quick presentation to the leadership team.

  • @EduHubSpot

    @EduHubSpot

    11 ай бұрын

    Loving your thought process. Gautham

  • @gayatrimarathe999
    @gayatrimarathe9997 ай бұрын

    Mayuresh Kotwal - WP Data Number of defects found - this is gathering data Finish date of activities - this is checking either planned or actual Number of change request completed WP Information Deliverable status - this is information as after comparing the planned and actual we will understand the status Implementation status of CR - this will be derived based on the comparison Status reports representing implementation status of CR - well, this is confusing but as electronic representation is not done, this should be under information WP Report Electronic Dashboard representing deliverable status - this is ELECTRONICALLY representing the status hence should be under report

  • @EduHubSpot

    @EduHubSpot

    6 ай бұрын

    Status reports representing implementation status of change request - WPR Gautham

  • @ilanchezian822
    @ilanchezian8225 ай бұрын

    Excellent

  • @EduHubSpot

    @EduHubSpot

    5 ай бұрын

    Thank you so much 😀 Gautham

  • @harishankar4005
    @harishankar4005 Жыл бұрын

    Well explained concept and so nicely done with an example. Nice one Gautham. As for answers, 1)Defects = WPD = These are defect numbers found and actuals "collected" (collect is the key word 2)Finish dates = WPD = Raw data with collection of dates . 3)Deliverable status = WPI = this is comparing the actual vs planned and according will give the deliverable status whether we are ahead or behind schedule etc. 4)# of CR's completed = WPD = these are numbers for the actuals completed and no comparison 5)Status of CR = WPI = Status means comparing current vs planned data and hence WPI 6) & 7 ) WPR = The name itself says reporting and Electornic representation so self explanatory

  • @EduHubSpot

    @EduHubSpot

    Жыл бұрын

    Loving your thought process. Gautham

  • @PradyDas
    @PradyDas Жыл бұрын

    Hi Gautham, thanks again for such a wonderfully explained video. Work Performance Data: Number of Defects Found, Finish Date of Activities, Number of Change Request Completed. Reasoning : These are Raw data and does not convey any status of the project on their own. Work Performance Information: Deliverable Status and Implementation Status of Change Request Reasoning: These signify some sort of status about the project which is derived by comparing raw project data Work Performance Reports: Status Reports representing Implementation Status of Change Request and Electronic Dashboard representing Deliverable Status Reasoning: These are electronic representation of the Work performance Information and hence these are Work Performance Reports.

  • @EduHubSpot

    @EduHubSpot

    Жыл бұрын

    Really loved your thought process. I need to steal this reasoning. Hahah !! Gautham

  • @priyankar3532
    @priyankar35327 ай бұрын

    Smashing the like 🎉

  • @EduHubSpot

    @EduHubSpot

    7 ай бұрын

    Thanks for loving the video. Gautham

  • @ajithkumaraj2516
    @ajithkumaraj25162 ай бұрын

    Superb!! Thanks for the excellent well presented explanation with samples. No books or notes needed anymore. Sorry over confident and happy after listening to the video... Kindly review and let me know your feedback...  Number of defects found. - WPD - Collecting Actual Raw Data  Finish dates of activities - WPD - Collecting Actual Progress - Raw Data  Deliverable status. - WPI - Comparing Data  Number of change request completed. - WPD - Collecting Actual Raw Data  Implementation status of change request. - WPI - Comparing Data  Status reports representing implementation status of change request. - WPR - Report presentation based on WPI  Electronic dashboard representing deliverable status. - WPR - Electronic Representation of WPI

  • @EduHubSpot

    @EduHubSpot

    2 ай бұрын

    Very impressive!! Gautham

  • @narawseedagaj
    @narawseedagaj Жыл бұрын

    Implementation status of change request - WPI , comparing with Plan on number of change request implemented so far

  • @EduHubSpot

    @EduHubSpot

    Жыл бұрын

    Very impressive!! Gautham

  • @damanpreetsyber6668
    @damanpreetsyber6668 Жыл бұрын

    Hi Gautham, very well explained. Numbers of Defects Found : is a work performance DATA. Finish Dates of Activities : is a work performance data. Deliverable Status :- is a work performance information Number of change request completed : Data Implementation status of change request : Information Status report representing implementation status of change request : Report Electronic Dashboard representing deliverable status : Report.

  • @EduHubSpot

    @EduHubSpot

    Жыл бұрын

    Keep up the good work!! Gautham

  • @azabohassan9593
    @azabohassan9593 Жыл бұрын

    1,4and 5 are wpi cos defects found are after implementation of raw data,no.of change request completed and implementation status of changes request are due to a result of implantation of wpd. Finish date and deliverables status are the wpd what's to be implemented Last two are report of what is implemented so that its easier for one to understand in simple way than many words.

  • @EduHubSpot

    @EduHubSpot

    Жыл бұрын

    Correct Answers : 1. Number of defects found - WPD 2. Finish dates of activities - WPD 3. Deliverable status - WPI 4. Number of change request completed - WPD 5. Implementation status of change request - WPI 6. Status reports representing implementation status of change request - WPR 7. Electronic dashboard representing deliverable status - WPR Gautham

  • @poojanewar2912
    @poojanewar2912 Жыл бұрын

    Hi Gautham, The concept is very well explained. Work Performance Data: 1, 2, 4 as these just represent the data and we cannot arrive at the status of the project Work Performance Information: 3, 5 as these represent the project status Work Performance Report: 6, 7 as these are the reports

  • @EduHubSpot

    @EduHubSpot

    Жыл бұрын

    Awesome job!! Gautham

  • @santoshpanda9762
    @santoshpanda9762 Жыл бұрын

    WPD- 1,2,3,4- All these are Raw observations, WPI-5,6- It is Status ( Comparison between Plan & Actual) WPR-7- Which is a electronic representation of Status Information The terms are well explained in a simple words

  • @EduHubSpot

    @EduHubSpot

    Жыл бұрын

    Correct Answers : 1. Number of defects found - WPD 2. Finish dates of activities - WPD 3. Deliverable status - WPI 4. Number of change request completed - WPD 5. Implementation status of change request - WPI 6. Status reports representing implementation status of change request - WPR 7. Electronic dashboard representing deliverable status - WPR Gautham

  • @DeyDiscoveries
    @DeyDiscoveries Жыл бұрын

    Implementation of change request-WPI

  • @EduHubSpot

    @EduHubSpot

    Жыл бұрын

    Keep up the good work!! Gautham

  • @SvetaBes
    @SvetaBes6 ай бұрын

    1 - data 2 - data 3 - information 4 - data 5 - data 6 - report 7 - report

  • @EduHubSpot

    @EduHubSpot

    4 ай бұрын

    5. Implementation status of change request - WPI Gautham

  • @kapoorvishal4446
    @kapoorvishal444610 ай бұрын

    Hi Gautham,  Number of defects found. --> WPD, as it gives the data information  Finish dates of activities --> WPD, same I am getting some data information  Deliverable status. --> WPI as it gives the status of delieverables  Number of change request completed. --> WPD, same I am getting some data information  Implementation status of change request. --> WPI as it gives the status of change request  Status reports representing implementation status of change request. --> WPR as it is report  Electronic dashboard representing deliverable status. --> WPR as it is report

  • @EduHubSpot

    @EduHubSpot

    9 ай бұрын

    Loving your thought process. Gautham

  • @MSK80J7
    @MSK80J77 ай бұрын

    1,2,4-Work performance data 3,5-Work performance information 6,7-Work performance report

  • @EduHubSpot

    @EduHubSpot

    6 ай бұрын

    Awesome job!! Gautham

  • @ajoydas9863
    @ajoydas98634 ай бұрын

    HI GAUTHAM ; Work performance data: 1,2,4 work performance information: 3,5 work performance report : 6,7

  • @EduHubSpot

    @EduHubSpot

    4 ай бұрын

    Very Impressive !! Gautham

  • @nitindhage856
    @nitindhage856 Жыл бұрын

    WPD - 1, 2 & 3 WPI - 4 & 5 WPR - 6 & 7

  • @EduHubSpot

    @EduHubSpot

    Жыл бұрын

    Correct Answers : 1. Number of defects found - WPD 2. Finish dates of activities - WPD 3. Deliverable status - WPI 4. Number of change request completed - WPD 5. Implementation status of change request - WPI 6. Status reports representing implementation status of change request - WPR 7. Electronic dashboard representing deliverable status - WPR Gautham

  • @naveengs1417
    @naveengs14179 ай бұрын

    Hi Gautham Number of Defects Found This is WP Data because - its represents the collection. Finish Dates of Activities This is WP Data as again its collection of data Deliverable Status This is WP Information - Status represents - we can compared Plan vs Actuals Number of Change request completed This is WP Data - represents collection of data Implementation status of change request This is WP Information - Status always shows Planned vs Actual Status reports representing Implementation status of change request This is WP Reports - Status reports is keyword here to call it as WPR Electronic Dashboard representing Deliverable status This is WP Reports - Electronic data representation is example of WPR thank you

  • @EduHubSpot

    @EduHubSpot

    9 ай бұрын

    Loving your thought process. Gautham

  • @shubhrasaxena3532
    @shubhrasaxena35328 ай бұрын

    1,2,4- work performance data (because these are actual number of defects found, actual finish dates and actual number of change requests completed) 3,5- Work performance information (actual progress status) 6,7- work performance reports- representation of project status

  • @EduHubSpot

    @EduHubSpot

    7 ай бұрын

    Loving your thought process. Gautham

  • @narawseedagaj
    @narawseedagaj Жыл бұрын

    First two are the WPD - no of defects and finish date are collected data

  • @EduHubSpot

    @EduHubSpot

    Жыл бұрын

    Awesome job!! Gautham

  • @pamelaakothondiek3812
    @pamelaakothondiek3812 Жыл бұрын

    1.Number of defects found is work performance information; 2. Finish dates of activity is work performance data as it is what will be used during progress and reporting; 3. Deliverable status is work information; 4. Number of change request completed is work performance report; 5. implementation status of the change request is work performance information; 6. status report representing implementation status of change request is a work performance report because it is electronically represented; 7. Electronic dashboard representing deliverable status is a work performance report because it is electronically represented.

  • @EduHubSpot

    @EduHubSpot

    Жыл бұрын

    Correct Answers : 1. Number of defects found - WPD Gautham

  • @mohinimahto3119
    @mohinimahto31197 ай бұрын

    Work Performance Data - 1,2,4 are data collected in terms of numbers what we fetch. Work performance Information- 3, 5 shows the status of the project , where we are or what actually has been covered so far. Work performance Report-6, 7 - shows how we represent the project status to the higher Management or the key stakeholders

  • @EduHubSpot

    @EduHubSpot

    7 ай бұрын

    Loving your thought process. Gautham

  • @arbendodajarben6923
    @arbendodajarben6923 Жыл бұрын

    from no.1 to no.5 are WPD, because are collecting informations and there are not comparing to anything. No.5 is WPI-1 , because compare one ork performance called "implementaion status of change request". No.6 is WPD- because collect the status of deliverable.

  • @EduHubSpot

    @EduHubSpot

    Жыл бұрын

    Correct Answers : 1. Number of defects found - WPD 2. Finish dates of activities - WPD 3. Deliverable status - WPI 4. Number of change request completed - WPD 5. Implementation status of change request - WPI 6. Status reports representing implementation status of change request - WPR 7. Electronic dashboard representing deliverable status - WPR Gautham

  • @narawseedagaj
    @narawseedagaj Жыл бұрын

    Deliverable status - WPI , compared with plan and actual

  • @EduHubSpot

    @EduHubSpot

    Жыл бұрын

    Great job!! Gautham

  • @washidali3122
    @washidali3122 Жыл бұрын

    WPD - 1, 2, 4 (Data) WPI - 3, 5 (Status) WPR - 6, 7 (Report)

  • @EduHubSpot

    @EduHubSpot

    Жыл бұрын

    Keep up the good work!! Gautham

  • @vidyasagarpinapa7713
    @vidyasagarpinapa7713 Жыл бұрын

    First three statements are work performance data,and next two statements are work performance information and last two statements are work performance reports.

  • @EduHubSpot

    @EduHubSpot

    Жыл бұрын

    Correct Answers : 1. Number of defects found - WPD 2. Finish dates of activities - WPD 3. Deliverable status - WPI 4. Number of change request completed - WPD 5. Implementation status of change request - WPI 6. Status reports representing implementation status of change request - WPR 7. Electronic dashboard representing deliverable status - WPR Gautham

  • @DeyDiscoveries
    @DeyDiscoveries Жыл бұрын

    Number of change request completed-WPI

  • @EduHubSpot

    @EduHubSpot

    Жыл бұрын

    Correct Answer : 4. Number of change request completed - WPD Gautham

  • @shivaniyadav2896
    @shivaniyadav2896 Жыл бұрын

    1 & 2 : WPD as thry are raw data 3, 4 & 5 : WPI as they are statuses of raw data turned into information 6 & 7 : WPR as they are representations to stakeholder(s) after calculation

  • @EduHubSpot

    @EduHubSpot

    Жыл бұрын

    Correct Answers : 1. Number of defects found - WPD 2. Finish dates of activities - WPD 3. Deliverable status - WPI 4. Number of change request completed - WPD 5. Implementation status of change request - WPI 6. Status reports representing implementation status of change request - WPR 7. Electronic dashboard representing deliverable status - WPR Gautham

  • @narawseedagaj
    @narawseedagaj Жыл бұрын

    Number of change request completed - WPD , actual number change request collected

  • @EduHubSpot

    @EduHubSpot

    Жыл бұрын

    Keep up the good work!! Gautham

  • @DeyDiscoveries
    @DeyDiscoveries Жыл бұрын

    Finished dates of activities- WPD raw data

  • @EduHubSpot

    @EduHubSpot

    Жыл бұрын

    Awesome job!! Gautham

  • @janeogbu5249
    @janeogbu52492 ай бұрын

    work performance data: 2- finish dates of activities 3 - deliverable status 5- implementation status of change all these are giving performance data about various work. Work performance information: 1- number of defects found 4 - number of change request completed these are comparing one data with another data given, like number of defects found in a total item, good one and the defected ones. Same with no 4. It is comparing change request completed with the total change request raised. Work Performance Report: 6- status report representing implementation of status of change request- reason ( it's a representation showing a report of an information. 7- electronic dashboard representing deliverable status- reason ( it is a report represented electronically

  • @EduHubSpot

    @EduHubSpot

    2 ай бұрын

    Correct Answers : 1. Number of defects found - WPD 2. Finish dates of activities - WPD 3. Deliverable status - WPI 4. Number of change request completed - WPD 5. Implementation status of change request - WPI 6. Status reports representing implementation status of change request - WPR 7. Electronic dashboard representing deliverable status - WPR Gautham

  • @sanatpatra
    @sanatpatra10 ай бұрын

    Hi Gautham, 1. Number of defects found Work performance Information - As this can be only found after looking in to work performance Data. 2. Finish dates of activities Work performance Data - Dates are part of your data. 3. Deliverable Status. Work performance Data - Status is also part of the data. 4. Number of change requests completed. Work Performance Data - This will also be reflected in the data. 5. Impelementation status of change request. Work Performance Data - All related statuses will be part of the data. 6. Status reports representing the implementation status of change requests. Work performance Report - This will be based on data collected and then a comparison is done on information and finally projected on the report. 7. Electronic Dashboard representing deliverable status. Work performance Report - Dashboard / Report will be obtained from the information. Cheers........

  • @EduHubSpot

    @EduHubSpot

    9 ай бұрын

    Correct Answers : 1. Number of defects found - WPD 2. Finish dates of activities - WPD 3. Deliverable status - WPI 4. Number of change request completed - WPD 5. Implementation status of change request - WPI 6. Status reports representing implementation status of change request - WPR 7. Electronic dashboard representing deliverable status - WPR Gautham

  • @katkepranav
    @katkepranav10 ай бұрын

    WPD - 2 WPI - 3, 1, 4, 5 WPR - 7, 6

  • @EduHubSpot

    @EduHubSpot

    10 ай бұрын

    1. Number of defects found - WPD 4. Number of change request completed - WPD Gautham

  • @remosumo12
    @remosumo123 ай бұрын

    WPD - Collecting Plan and Collecting Actual Progress 1. Number of Defects found. 2. Finish Dates of Activities. 4. Number of CRs completed. WPI - Comparing Plan and Actual Progress 3. Deliverable Status. 5. Implementation status of CR. WPR - An electronic representation of WPI 6. Status reports representing the implementation status of CR. 7. Electronic Dashboard representing Deliverable Status.

  • @savitachetan12
    @savitachetan12 Жыл бұрын

    Hi Gautham, Work Performance Data: 1, 2, 4 give data of planned or actual Work Performance Information: 3, 5 give compared result of the data I:e status information Work Performance Report: 6, 7 these are dashboard representation of information .

  • @EduHubSpot

    @EduHubSpot

    Жыл бұрын

    Very impressive!! Gautham

  • @narawseedagaj
    @narawseedagaj Жыл бұрын

    Last two are WPR - because status report and electronic report are the key words

  • @EduHubSpot

    @EduHubSpot

    Жыл бұрын

    That is exactly how you should think. Gautham

  • @AlokKumar-li6jz
    @AlokKumar-li6jz Жыл бұрын

    Hi Gautham below are the answers with explanation: 1,2,4 are WPD here data is collected in the form of number, dates as we are collecting actual progress 3,5 is WPI as we are getting the progress through status 6,7 is WPR over here representation of work performance information

  • @EduHubSpot

    @EduHubSpot

    Жыл бұрын

    Very impressive!! Gautham

  • @nishadibrahim5347
    @nishadibrahim534711 ай бұрын

    1. WPD - this represent raw data on the number of defects 2. WPD - represent raw data of finish dates 3.WPI - this represent the comparison of the plan with the actual progress 4. WPD - Raw data in the form of change request numbers 5.WPI - this mentions about the status 6.WPR - states about the status report 7.WPR - Electronic report of WPI

  • @EduHubSpot

    @EduHubSpot

    10 ай бұрын

    Loving your thought process. Gautham

  • @ashrutisaxena8725
    @ashrutisaxena8725 Жыл бұрын

    WPD- 1,2,4 as they represent raw data WPI- 3,5 are WPI as they are comparing the status WPR: 6,7

  • @EduHubSpot

    @EduHubSpot

    Жыл бұрын

    Very impressive!! Gautham

  • @kainaatayranr6000
    @kainaatayranr600010 ай бұрын

     Number of defects found.- WPD (just no. of defects found is a collection of Data)  Finish dates of activities- WPD (This is again im collecting the data)  Deliverable status.- WPI (Im sharing the status of a deliverable which is a Information)  Number of change request completed.- WPI( No. of changes completed int he sense actioned, which is nothing but information  Implementation status of change request.-WPI( Information which helps in comparing with actuals)  Status reports representing implementation status of change request.- WPR  Electronic dashboard representing deliverable status- WPR ( Any status flashed on electronics dashboard using data & information is called report status)

  • @EduHubSpot

    @EduHubSpot

    9 ай бұрын

    Correct Answers : 1. Number of defects found - WPD 2. Finish dates of activities - WPD 3. Deliverable status - WPI 4. Number of change request completed - WPD 5. Implementation status of change request - WPI 6. Status reports representing implementation status of change request - WPR 7. Electronic dashboard representing deliverable status - WPR Gautham

  • @DeyDiscoveries
    @DeyDiscoveries Жыл бұрын

    Deliverable status -WPD

  • @EduHubSpot

    @EduHubSpot

    Жыл бұрын

    Correct Answer 3. Deliverable status - WPI Gautham

  • @parbodhkumar
    @parbodhkumarАй бұрын

    Item 1 - WPD (it is an individual raw observation) Item 2 - WPD (it is an individual raw observation) Item 3 - WPI (Because we reach useful information after analyzing data) Item 4 - WPD (it is an individual raw observation) Item 5 - WPI (Because we reach useful information after analyzing data) Item 6 - WPR (Because it represents the status of implementation. Even if it is not mentioned as electronic representation but tells status) Here, I am confused about whether it is mandatory to look for the word electronic to designate it as WPR. Kindly clarify. Item 7 - WPR (Here it is mentioned that it is an electronic dashboard that represents status)

  • @EduHubSpot

    @EduHubSpot

    Ай бұрын

    That is exactly how you should think. Gautham

  • @Nagulsharifshaik-gh8te
    @Nagulsharifshaik-gh8te Жыл бұрын

    Number of defects found- work performance data as its execution level data. Finish dates of activities- WPD as it seems planning for the dates Deliverable status -WPD planned Number of change request completed- WPD its in execution Implementation status of change request.-wpr showing the status Status reports representing implementation status of change request- WPI showing the completion. Electronic dashboard representing deliverable status- wpr showing the dashboard.

  • @EduHubSpot

    @EduHubSpot

    Жыл бұрын

    3. Deliverable status - WPI 5. Implementation status of change request - WPI 6. Status reports representing implementation status of change request - WPR 7. Electronic dashboard representing deliverable status - WPR Gautham

  • @aditibhargava8307
    @aditibhargava8307 Жыл бұрын

    WPD - 1, 2 and 4 they ar raw data on number of defects and dates WPI - 3 and 5 . They speak of status WPR - Last two as they show reports

  • @EduHubSpot

    @EduHubSpot

    Жыл бұрын

    Keep up the good work!! Gautham

  • @samsonolufemiajayi650

    @samsonolufemiajayi650

    Жыл бұрын

    Number 1,2,4-WPD - raw data Number 3and 5-WPI. _deliverable status NUMBER 6and 7-WPR _electronic representation of WPI

  • @ketansoni8246

    @ketansoni8246

    Жыл бұрын

    WPD 1;2 & 4 RAW DATA WPI 3 &5 status of spk WRP 6& 7 representation of WPI

  • @EduHubSpot

    @EduHubSpot

    Жыл бұрын

    @@samsonolufemiajayi650 : This is great Samson Gautham

  • @EduHubSpot

    @EduHubSpot

    Жыл бұрын

    @@ketansoni8246 Great job Soni Gautham

  • @sajidforever
    @sajidforever8 ай бұрын

    1,2,4 - WPD - raw data obtained without comparison 3,5 - WPI - status after comparison with Planned vs Actual 6,7 - WPR - keyword are reports and dashboard

  • @EduHubSpot

    @EduHubSpot

    7 ай бұрын

    Very impressive!! Gautham

  • @jagdishpurohit928
    @jagdishpurohit928 Жыл бұрын

    Hi Gautham, well explained; short & simple.... WPD(Data)-1, 2, 4 WPI(Status)- 3 , 5 WPR(Reports/Electronic version)-6,7

  • @EduHubSpot

    @EduHubSpot

    Жыл бұрын

    Fantastic job Jagdish Regards, Gautham

  • @yashtambe4263
    @yashtambe42639 ай бұрын

     Number of defects found. - WFD - its a actual data  Finish dates of activities - Its and WFD.. its a Actual finished data  Deliverable status. - Its WFI - Status of the project that is comparison of plan and actual  Number of change requests completed. - WFD - its a actual data  Implementation status of change request. - WFI - Its a comparison of total change request and actual completed CRs  Status reports representing the implementation status of change request. - WFR  Electronic dashboard representing deliverable status. - WFR --- Its presentation of WFD

  • @EduHubSpot

    @EduHubSpot

    9 ай бұрын

    Very impressive!! Gautham

  • @naveenlakkimsetti2759
    @naveenlakkimsetti2759 Жыл бұрын

    Number of defects found. - WPD, Reason- As per the keyword of WPD collecting the defects in this case Finish dates of activities - WPD, Reason - It is also part of collecting the raw data Deliverable status. - WPI, Reason - To know the status of the deliverable we need to compare with actual vs planned Number of change request completed. - WPD, Reason - It will not give the status of CR, here we are just collecting the no . of CR completed Implementation status of change request. - WPI, Reason - Status of the CR status can get from Planned vs Actual Status reports representing implementation status of change request. - WPR, Reason-Representation of data Electronic dashboard representing deliverable status. - WPR, Reason - Representation of data

  • @EduHubSpot

    @EduHubSpot

    Жыл бұрын

    That is exactly how you should think. Gautham

  • @DeyDiscoveries
    @DeyDiscoveries Жыл бұрын

    Last two are WPR

  • @EduHubSpot

    @EduHubSpot

    Жыл бұрын

    Awesome job!! Gautham

  • @DeyDiscoveries
    @DeyDiscoveries Жыл бұрын

    Number of defeats found-WPD. Raw data

  • @EduHubSpot

    @EduHubSpot

    Жыл бұрын

    Great job!! Gautham

  • @vengateshbabuvijayakannan9229
    @vengateshbabuvijayakannan9229Ай бұрын

    Work Performance Data : Number of defects found, --> Collecting Actual Progress finish dates of activities --> Collecting Actual Progress No. of change request completed --> Collecting Actual Progress Work Performance Information - Deliverable Status --> Comparing Plan and Actual Progress Implementation status of change request --> Comparing Plan and Actual Progress Work Performance Report : Status reports representing implementation status of change request. --> An Electronic Representation of Work Performance Information Electronic dashboard representing deliverable status.--> An Electronic Representation of Work Performance Information

  • @EduHubSpot

    @EduHubSpot

    Ай бұрын

    Loving your thought process. Gautham

  • @Vimal-Purbia
    @Vimal-Purbia2 ай бұрын

     Number of defects found. - WPD - Because its raw data which tell that number of defects found but doesn't tell its current status  Finish dates of activities - WPD - Its planning that has been done for each activities  Deliverable status. - WPI - It gives the information of actual deliverable status of the work  Number of change request completed. - WPI - It gives the status of no. of change requested completed  Implementation status of change request. - WPI - Prividing the information of change request, how it got implemented  Status reports representing implementation status of change request. - WPR - It is the report generated to show the status of CR, how it got implemented  Electronic dashboard representing deliverable status. - WPR - Again, its electronic dashboard which is example of WPR Please correct me if I am wrong.

  • @EduHubSpot

    @EduHubSpot

    2 ай бұрын

    4. Number of change request completed - WPD Gautham

  • @elgyalex6811
    @elgyalex68114 ай бұрын

    Number of defects found - WPD Finish dates of activities - WPD Deliverable status- WPI Number of change request completed- WPD Implementation status of change request - WPI

  • @EduHubSpot

    @EduHubSpot

    4 ай бұрын

    Awesome Job !! Gautham

  • @muzawarm
    @muzawarm Жыл бұрын

    WP Data 1 = No of defects found , WP data 2 = Finish Date activities, WP data 3 = No of change requests ( identified defects requested for rework) --- This is all WP data as it is giving us info about project activities , defects found tells us from list of activities few were defected and not completed or delivered successfully, No of change request tells us that identified defects are requested for rework...... this overall is collecting data and actual progress of project activities,,, NOW Work Perf Info = WP info 1 = Project is out of schedule as few activities were not successfully delviered and have defects i.e No of defects in , WP info 2 = Change request for no of defects identified. as these 2 WP info's are derived by comparing the data with actual progress, Now reports are WP report 1 = deliverable status i.e out of list of activities planned e.g 10 activities 4 were defects & WP report 2 = change request for 4 defects implementation status of rework if all 4 were reowrked successfully or not.

  • @EduHubSpot

    @EduHubSpot

    Жыл бұрын

    Correct Answers : 3. Deliverable status - WPI 4. Number of change request completed - WPD 5. Implementation status of change request - WPI 6. Status reports representing implementation status of change request - WPR 7. Electronic dashboard representing deliverable status - WPR Gautham

  • @user-dq8ge3fc7w
    @user-dq8ge3fc7w Жыл бұрын

    1 2 4 WORK PERFORMANCE DATA (these are actual and planned data) 3 5 WORK PERFORMANCE INFORMATION (these are status) 6 7 WORK PERFORMANCE REPORT (these are electrocic presentations)

  • @EduHubSpot

    @EduHubSpot

    Жыл бұрын

    Awesome job!! Gautham

  • @mananjain1505
    @mananjain150510 ай бұрын

    1) Number of defects found- WPI 2) Finish date of activities- WPD Deliverable status- WPI 3) Number of change request completed- WPI 4) Implementation status of change request - WPI 5) Status report representation implementation status of change request - WPR;

  • @EduHubSpot

    @EduHubSpot

    10 ай бұрын

    Correct Answers : 1. Number of defects found - WPD 2. Finish dates of activities - WPD 3. Deliverable status - WPI 4. Number of change request completed - WPD 5. Implementation status of change request - WPI 6. Status reports representing implementation status of change request - WPR 7. Electronic dashboard representing deliverable status - WPR Gautham

  • @shaleenm2k
    @shaleenm2k Жыл бұрын

    Number of defects found work performance data Finish dates of activities work performance data Deliverable status work performance information Number of change request completed. work performance data Implementation status of change request. work performance information Status reports representing implementation status of change request. work performance report Electronic dashboard representing deliverable status. work performance report

  • @EduHubSpot

    @EduHubSpot

    Жыл бұрын

    Very impressive!! Gautham

  • @umamaheswariannadurai8462
    @umamaheswariannadurai84622 ай бұрын

    1) WPD: It is raw data 2) WPD: It is raw data 3) WPI: Information derived from data 4) WPD: It is raw data 5) WPI: Information derived from data 6) WPR: Report presented using Info 7) WPR: Report presented using Info

  • @EduHubSpot

    @EduHubSpot

    2 ай бұрын

    Very impressive!! Gautham

  • @SujataManish-yr7bo
    @SujataManish-yr7boАй бұрын

    " Number of defects found. WPD  Finish dates of activities WPD  Deliverable status. WPI  Number of change request completed. WPD  Implementation status of change request. WPI  Status reports representing implementation status of change request. WPI  Electronic dashboard representing deliverable status. WPR

  • @EduHubSpot

    @EduHubSpot

    Ай бұрын

    Loving your thought process. Gautham

  • @narawseedagaj
    @narawseedagaj Жыл бұрын

    Implementation status of change request - WPI , comparing with Plan on number of change request implemented so far

  • @EduHubSpot

    @EduHubSpot

    Жыл бұрын

    Very impressive!! Gautham