Topping Ceremony, Impact Report, Conduit Install & More! 24 May 2024 Giga Texas Update (07:35AM)

Автокөліктер мен көлік құралдары

Gigafactory Texas! This is where Model Y’s, and Cyber Truck production happens and soon, the Next Generation Car!
Happy Memorial Day Weekend! This is the time to remember and give thanks to those who have served yet never made it home. Because it is Memorial Day on Monday, I am not planning on flying on 27 May and will resume on 29 May.
Although I was going to announce my trip to Starbase next week for SpaceX's Starship launch #4, but I just received notice from SpaceX that the launch has moved from 1 June to 5 June, so I'll be adjusting my trip plans. For now, it looks like I'll be headed to Starbase on 3 June and be gone the entire week.
In the video Intro, we briefly discuss the 2023 Tesla Impact Report, which is available as a summary or a full 159-page document. I go over a few highlights tat pertain to Giga Texas and the Corpus Christi Lithium Plant, but there is just too much information to summarize, so I recommend you look at either the official summary document of the full 150-page report as there are many subjects and items of interest.
Timestamps:
Drone flight overview with discussion & illustration: 0:06 to 4:47
Drone flight footage & infographics: 4:53 to 30:42
A few other highlights from today:
At Giga Texas, we see some indications that Tesla was getting ready for the Memorial Day weekend with a reduction in production of the Cybertrucks, however, Model Y production seemed a tick higher than what I've seen in the past few weeks. I saw a large number of Model Y's exiting the factory and getting prepared to move to the outbound lot. I did not see any Cybertrucks exiting the factory and on the east side there were fewer Cybertrucks visible as well.
The south end extension shows crews busy inside & out! On the roof, another large section of the final roofing materials was being installed at the time of my flight, while we also se almost all of the roof decking has now been installed across the rest of the roof, cutting off our views into the structure. On the ground floor, we see crews finishing another large concrete pour, while on the 3rd floor, we see scaffolding with plastic sheeting has been installed.
Also on the south end, more glass panels have been installed on the southwest corner, and framing around the "entrance" area is underway. More of the glass parapet wall sections have been installed on the south side, while more large cooling pipes have been delivered into the west side of the second floor. Finally, crews were making quick work installing the Fiber Reinforced Plastic (FRP) Pipe superstructure on the reinforced roof of the structural cooling platform.
There was a display of Giga Texas produced vehicles around the Cybertruck graffitied trailer across from the main entrance. In this general area, we also see crews installing more of the orang flexible conduit for fiber optic cables running the length of the west berm from the north Cyberberms all the way under the south bridge.
Conduit installation and trenching was moving rapidly on the north end of the main factory, now a large section being installed in the north parking lot and landscaped area. This is working it's way to the south to connect in with a similar conduit installation just north of the casting machine section and also under Tesla Road.
Finally, following up on large IDRA deliveries to the DIE Shop on my 22 May video, another large, crated item on a heavy-load trailer had just arrived this morning and was being readied for movement into the DIE Shop so the bridge cranes can lift it off the trailer. This is likely a continuation of the IRDA equipment being delivered.
Thank you for watching and I hope this has been informative, educational, and entertaining for you. If you would like, please consider supporting me via Patreon (link is in the description of this video and in the video itself) so I can continue to make and share these incredible videos.
Sources used in this video:
Tesla Impact Report:
Summary and Full Report Link:
www.tesla.com/impact
Full Report Direct Link:
www.tesla.com/ns_videos/2023-...
Follow me on
Patreon / joeslastchancegarage
X @JoeTegtmeyer
Instagram (Joe’s Last Chance Garage) for the latest updates: #joeslastchancegarage
Facebook Joe Tegtmeyer and Joe’s Last Chance Garage
If you are interested in purchasing a Tesla vehicle or solar product, please consider using my referral code!
www.tesla.com/referral/joe66892
Be sure to check out additional Texas Gigafactory footage on these channels:
@Jeff Roberts
@Brad Sloan
Video, photos, illustrations, and commentary on this video is by me, Joe Tegtmeyer unless otherwise annotated.
Music in this video is obtained from the KZread free and unrestricted and royalty-free use library. Ending song is Mr. Sunny Face - Wayne Jones
Drones used are DJI Mini 2, Mavic Air 2 & Air 3.
Drone flight over Giga Texas is with permission of Tesla and CEO Elon Musk

Пікірлер: 78

  • @VintageFilmChannel
    @VintageFilmChannel23 күн бұрын

    Every design change on the chassis probably requires a new crash test, or series of tests. Having this capability here gives very fast turnaround on new design iterations...

  • @ohtoah
    @ohtoah22 күн бұрын

    Across the water retention filtration pond by the crash test facility, if you remember the over flow pipes that were installed they extended the pipes out a long way. I believe that the plan is to add a road along that side of the pond that that extends out to connect to the new road that is planned by the lone tree.

  • @budgetaudiophilelife-long5461
    @budgetaudiophilelife-long546123 күн бұрын

    🙋‍♂️THANKS JOE FOR THE UPDATES 🤗💚💚💚

  • @JoeTegtmeyer

    @JoeTegtmeyer

    23 күн бұрын

    You're welcome!

  • @richmargin6082
    @richmargin608223 күн бұрын

    Every inch that has a building or concrete is not even half of the campus that they own. There is so much more to be built out. Crazy!!

  • @michelangelobuonarroti916

    @michelangelobuonarroti916

    23 күн бұрын

    The buildout will still be happening ten years from now.

  • @earthwizz

    @earthwizz

    22 күн бұрын

    I thought it was odd having the concrete plant so far away. Turns out it's in the middle of the site. Definitely more to be built.

  • @DessieDoolan
    @DessieDoolan23 күн бұрын

    Thanks Joe 2:28. Casting, east. In Brad’s video yesterday a forklift with a bin of casting biscuits was seen turning into Casting. New furnaces may be accepting the scrap now. Up until now all casting scrap was sent off site. Tesla claim of use of ’Non Telsa components including wheels’ doesn’t seem to sit with the highly specific alloy used in the gigacastings. I think they mean the aluminum can be sourced from recycled components, not that aluminum wheels can be tossed into the furnace. 5:06. Southend, east. Level 1. Concrete placement on the elevated floor behind the scaffold stair. Glimpse at 8:15. 7:22. BIW, roof. Scaffold platform. 2 spools/reels/drums of cable under blue tarpaulins. Spools are on rollers, ready to start paying-out the cable from the platform. 7:41. Southend. Cooling tower. To the left. 8 stacks of curved material would be the air outlets. ‘Fan stack’ as shown on the Evaptech images. Top deck sheets trimmed to circular shapes for the fan stacks. 10:32. Southend. Central Structure. Level 3 bridge crane is visible. 2 bridge cranes installed. Suspended scaffold behind. Left. Under roof. Scaffold stairs up to a suspended scaffold platform. 11:03. Southend. Central Structure. Level 1. Left. Heavy steel pipe supports suspended from the underside of Level 2, would be for the big pipes. Studwall being constructed atop the east-west retaining wall. Right, machinery moving around on the finished floor. 12:31. Perimeter road. No fenced-off areas. TBM is under here somewhere. Tunnel portal in the apron now looking unlikely. 13:46. Westside, Tunnel Project. Conveyor Belt Cassette. Bottom beam has risen 3’ - 4’ feet 0.9 - 1.2mm since Wednesday. Using David Salisburys progress estimate from Wednesday, the TBM must now be under the perimeter road. No areas being cordoned off. So its safely deep enough. 16:32. Westside. Pipe Fabrication shop. Smaller pipes may be the lines to individual components in the Data Centre. 16:35. Westside, storage. Left. Stainless steel troughs. Possible part of the baghouse filtering equipment. A lot of this gear could be associated. Ductwork and steel frames at 16:14 also. 16:49. Far west. Worlds largest cow-pats. Tunnel spoil dump site. Spread out to dry. 20:55. Northend. Highway exit. ‘FBL’ marked on the road. Something to do with the Fibre Optic cable location. 21:14. Battery, north. Second Alimak (construction elevator) has been removed. Spool of flexible orange conduit. Pair of tricyclists. 22:43. Tesla Road. Black pipes on the trailer. Same seen at the Southend, west in Joe’s photos. 25:48. Cathode, Plant Platform. Chiller having the pipes connected. 26:54. Far east. Left. Conduits in the trench. 29:49. Parking Garage site. Bottom right. Huge steel pipes in red oxide paint. Compare the diameter to the size of the front-end loader pushing gravel around.

  • @scottgaree7667

    @scottgaree7667

    22 күн бұрын

    16:32 Yes, those look like the manifolds to run water to the rows of racks and then likely split off those to individual racks. Within the rack will be a heat exchanger. There is a separate coolant loop within the rack with manifolds to feed coolant to water blocks on the components. Separate loops allow a lower volume of more exotic coolants to be used in the racks (even different coolants as needed), while using water in the main loop to carry the heat away from the racks. Much lower volume of exotics and large volume of water with all the cost and inertness benefits. Also, if you get a leak in a rack loop on a long weekend you don't come back to find your entire coolant supply running across the floor. (Datacenter humor. 😅) You also still need a good volume of regular air handlers to provide cooled ambient air to the non-liquid cooled components. This is assuming conventional racks using coolant blocks, but another possible option is immersive cooling, where there are no fans or air movement (besides keeping the carbon units comfortable.) I like to call that "Chicken-fried compute." 🤣

  • @DessieDoolan

    @DessieDoolan

    22 күн бұрын

    @@scottgaree7667 16:32. Great information! I'm beginning to get a picture in my mind about what it will look like. Flow and return pipes. Would these be on the same level? Or is flow above and return below to take advantage of gravity? Intermediate pumps on these lines, or is all the pumping done back at the Cooling Tower Structure?

  • @scottgaree7667

    @scottgaree7667

    22 күн бұрын

    @@DessieDoolan My limited knowledge is from the compute side of things. I suspect there has to at least be some intermediate pumping to deal with variance in cooling demand of branches. Looks like the DC is higher than the chiller plant, so gravity will help on return, no matter how the branch lines are deployed. All the chilled water loops I've actually seen in DCs has been low (at or under floor), but was used for air handlers. At a minimum it makes servicing easier. I've seen R&D labs for in-rack cooling, but wouldn't expect it to be indicative of production solution arrangements. Interestingly the additional weight due to hardware density and liquids can be significantly higher than legacy DCs, so greenfield like this can be built to deal with it more easily.

  • @DessieDoolan

    @DessieDoolan

    22 күн бұрын

    @@scottgaree7667 Weight. Well they have designed for it. The columns in this area were beefed up. Not obvious if the beams were. Any thoughts on the bridge cranes? Are cranes a feature of Data Centers generally?

  • @DessieDoolan

    @DessieDoolan

    21 күн бұрын

    @@scottgaree7667 Great opening shot in Brad's 25 May video at 0:01, shows the cooling tower lower platform is half or less the height of Level 2 of the extension.

  • @frankscruggs9089
    @frankscruggs908922 күн бұрын

    at timestamp 19 minutes there are approximately 33 cyber trucks per row meaning there are nearly 200 in this part of the outbound lot

  • @TeslaElonSpaceXFan
    @TeslaElonSpaceXFan23 күн бұрын

    Thank you Joe! Great content. 🙂

  • @JoeTegtmeyer

    @JoeTegtmeyer

    23 күн бұрын

    You're very welcome! Have a great Memorial Day Weekend!

  • @OPENLAND-kt1zr
    @OPENLAND-kt1zr22 күн бұрын

    It seems like the digging never ends

  • @davidsalisbury50
    @davidsalisbury5022 күн бұрын

    Boring tunnel;: Overall about 108 stacks of (3) liner plates remaining. Although some are painted red, which generally denotes that they are rejects that cannot be used on the permanent works (if we see these being used it almost certainly means they are nearing the end and these will eventually be removed). 108 less say 20 for rejects = 88 stacks, 44 rings, 66m. The white tube containing the extended ventilation cassette has gone from behind the Operations Control container. An empty one can be seen at 14:12 in the mid far right of the picture. this means they have extended the ventilation. The yellow vent extends from where it can be seen at the portal to the back of the TBM backup (the TBM backup has a separate booster fan along its length). The yellow vent ducts tend to be in 100m (330'), which I originally expected, but they can be 150m (500') lengths. If 150m that would agree with the estimated tunnel over all length of 245-250m (95-100m for the overall length of the TBM and back-up). it would have needed a couple of hours to change the ventilation cassette. The main power cable seems to be used up with a new coil awaiting to extend the main power. this will take the best part of a day as this needs a strong joint that can be pulled along the tunnel wall. Conveyor cassette has risen approximately 3.8m since 4th May. 3.8m x 26 = 99m. Added to the estimated tunnel length of 150m on 4th May equals 249m excavated. from google maps that would put the cutterhead at the fence line just behind the cars on the edge of the perimeter road (again, I wouldn't want my car parked there right now!). The 66m of remaining segment takes it right to the edge of the extension building. Lot of activity in the extension structure but not in the bay neared the existing building, more reason to think that this will become the tunnel ramp once the TBM has been removed.

  • @DessieDoolan

    @DessieDoolan

    22 күн бұрын

    I've been quoting the tunnel being under the perimeter road. I'll need to correct that in future comments. About another 33m then to the east side of the perimeter road. No fenced off area to suggest the TBM is approaching. Can it be assumed that the TBM is deep enough that it won't disturb the ground surface?

  • @scottgaree7667

    @scottgaree7667

    22 күн бұрын

    @@DessieDoolan 10:30 A ways into the building still looks unsurfaced? This opening in the perimeter beam could be where the tunnelling equipment is driven out after surfacing in that area.

  • @DessieDoolan

    @DessieDoolan

    22 күн бұрын

    @@scottgaree7667 My 'current' calculation is that for the TBM to emerge even right at the perimeter grade beam location would require it to gain 36' in 110', which seems excessively steep to me. I'll bore you with the math if you like! The tunnel portal being deep inside the extension where concrete has yet to be placed would seem the logical conclusion.

  • @davidsalisbury50

    @davidsalisbury50

    22 күн бұрын

    @@DessieDoolan It doesn't make sense to me. I assume the TBM is on its way back up. Should be near the surface (within 3-5m) now. If that were the case I would be having areas cordoned off, stopping parking and possibly diverting the traffic on the road. I have seen a slightly smaller than this TBM start the cutterhead, loose the face pressure through the screw, and suck the whole world above it down into the ground (The TBM had flood doors to stop the process but not before 100 or so cubic meters of soil had collapsed in on itself). Happens in a couple of seconds in sandy/clay wet ground. There were little kids playing on the ground directly above just minutes prior to this happening, a puddle had formed out of nowhere (from over excavation of the previous ring), the kids though it was cool and started playing in it, our foreman saw the potential risk and barked at the kids to tell them to get away. A very close call that still haunts me 35 years later.

  • @davidsalisbury50

    @davidsalisbury50

    22 күн бұрын

    @@DessieDoolan But they don't appear to have the segments to get that far! My calculations may be way off of course. I have seen your previous numbers regarding the constraints above the TBM. It seems too late to get it to the surface before that point. The next few days will tell. My end of May prediction for the breakthrough is still looking possible.

  • @tonyvelasco5732
    @tonyvelasco573223 күн бұрын

    Additional light poles going up on the newest part of the top floor of the parking garage yesterday and today!

  • @Chicagosand
    @Chicagosand22 күн бұрын

    The world is changing before our eyes 😳

  • @nathanprice4568
    @nathanprice456821 күн бұрын

    Nice

  • @lylestavast7652
    @lylestavast765223 күн бұрын

    I think that triangle shaped block on the west side would be a good location for a publicly accessible charger site - right off the main road...

  • @benguthrie49
    @benguthrie4922 күн бұрын

    Thanks Joe

  • @DessieDoolan

    @DessieDoolan

    22 күн бұрын

    1.30am!

  • @benguthrie49

    @benguthrie49

    22 күн бұрын

    @@DessieDoolan Odd as I am, I typically go for a 5 or 6 mile walk sometime between midnight and 4 am. extreme night owl. I often catch late jazz til 2 or 3 am and it's easier to keep the schedule most days.

  • @DessieDoolan

    @DessieDoolan

    22 күн бұрын

    @@benguthrie49 I'm the opposite. 11pm is a late night for me!

  • @lourdessilva6442
    @lourdessilva644223 күн бұрын

    Sem palavras esse documentário adoro seu trabalho sucesso esse conteúdo es muito interessante e sim es trabalhar em prol da preservação da raça humana

  • @DavidJohnson-tv2nn
    @DavidJohnson-tv2nn22 күн бұрын

    Here is some interesting information that I got in a reply to my one of my comments on Brad's video 5/23/24... "Yep we start on the 30th, 4 UPS per room with 240 Batteries per UPS, 24 Rooms per floor, for 3 floors.. So 96 UPS per floor, 23,040 Batteries per floor.. 288 UPS and 69,120 batteries… Not including extra rack batteries…" His reply was in response to my comment..... "There is a new permit for the data center..... Special Project Permit #2024-0996 SX-000608 - SX - Battery Storage UPS Submittal Date 5/23/2024"

  • @hal3137
    @hal313723 күн бұрын

    Awesome joe enjoy.

  • @pgskretting1216
    @pgskretting121622 күн бұрын

    Thanks Joe. Really like your videos

  • @douggolde7582
    @douggolde758222 күн бұрын

    You ever do a touch and go on the helipad?

  • @douglasmurphy6385
    @douglasmurphy638522 күн бұрын

    Thanks!

  • @JoeTegtmeyer

    @JoeTegtmeyer

    21 күн бұрын

    Thank you again Douglas!

  • @ryer8477
    @ryer847722 күн бұрын

    When the lights are on, could you try to take a look inside of the tunnel from the outside?

  • @DavidJohnson-tv2nn
    @DavidJohnson-tv2nn23 күн бұрын

    Thanks Joe! Rooftop cable trays/ladders: @ 7:27 Two cable spools on the work platform, first spotted by Dessie yesterday. Cable pull coming soon. The double stack cable trays/ladders by the parapet wall run the full length from angled corner to angled corner. Google Earth shows the distance to be about 3,600 feet! The south termination of the cable run is @ 7:49 This will allow medium voltage (MV) cables at 24,900 volts, to bring power from the north end of the building to the data center in the south extension. Cooling structure: @7:42 (Bottom left) Looks like stacks large grey fan shroud segments to be assembled on top the structure for the cooling fans. Fiber optic HDD bore: @ 12:02 (Bottom), 12:08 (Bottom of screen, middle of the road), and 12:12 (Bottom) Joe.... Any chance you can check the other side of the river if time permits? Thanks. I doubt that the bore ends here. 😊 All part of a very long HDD bore for fiber optic cables. Speculating that there may actually be two separate bores. One from the south and one from the north, in order to maintain redundancy for the data center. The north bore beginning @ 21:01 (Left). Northside of casting: @ 21:43 Hoping to get a look into the open vault once the forms are removed to get a conduit count. This is the vault where 12 conduits enter, but it appears that only 8 conduits exit. Also @ 21:43 Concrete pour around the vaults by the building. @ 22:19 Duct-banks being constructed across parking lot. @ 22:30 Another vault location. Black conduit spacers can be seen laying on the ground.

  • @andreandre1051
    @andreandre105122 күн бұрын

    Merci👍👍👍

  • @benguthrie49
    @benguthrie4922 күн бұрын

    Does anyone know where the nearest/largest communications hubs are which could provide internet access?

  • @AMeierhoefer
    @AMeierhoefer23 күн бұрын

    Thanks Joe. Great video. MY production seems to have almost stopped and CT is still early and ramping. It feels like 10000 people to make the number fo CT you are showing is massive overkill. Do you think many more than 10% were fired? Not making MY at Giga Texas could mean a horrible Q2, especially because China numbers are low, and Europe is stalling, so maybe TSLA will really slow a lot when we find out in Jul. Do your sources tell you anything about this noticeable slow down in manufacturing?

  • @Nphen

    @Nphen

    22 күн бұрын

    Probably slowing things down now and tanking this quarter because there's already been so much bad news. If sales don't pick up in July, they can cut prices until the new model is ready. Sometime this summer Cybertruck will get a $20k price cut. Then demand will explode. They may well be getting the second CT line ready for the "final" ramp to 1,000 per day.

  • @AMeierhoefer

    @AMeierhoefer

    21 күн бұрын

    @@Nphen I agree on the first part but I really have a hard time seeing many people in this economy wanting to spend $70K or even $60K on a truck

  • @kevroll99
    @kevroll9922 күн бұрын

    Joe, do you know what the tunnel is for? Vehicle transport? And also what the main reason/use for the South extension? I heard a supercomputer but nothing else, I thought it was going to be for the 25k vehicle and the tunnel was for moving them over to the final checkpoint area and bldg.

  • @dariomarquez12
    @dariomarquez1223 күн бұрын

    Joe, which is the name of the song you use in many parts of the video? Thx!

  • @kennycressler611
    @kennycressler61122 күн бұрын

    Do you have any idea how far they went with the boring tunnel so far?

  • @BlazerRox
    @BlazerRox21 күн бұрын

    No more Cybertrucks in the parking garage?

  • @rory-red
    @rory-red23 күн бұрын

    HI JOE!!!! Fiber Optic cable normally referred to be a ISP Backbone

  • @ernestgalvan9037

    @ernestgalvan9037

    22 күн бұрын

    Yeah, fiber used too be the domain of mega-corporations and back-haul and back-bone systems … Now fiber is becoming common in residential construction… I have a fiber running from the wiring closet in front to the wiring closet in the back of my house, and another going to the detached garage/workshop.

  • @RanchReed

    @RanchReed

    22 күн бұрын

    Many normal businesses are connected with Fiber. Large school districts have a backbone of fiber throughout, for example. Regular Ethernet over copper wire is only good up to 100 meters. Multi-mode fiber is good for about 220 meters. Single mode fiber is good for 10k and beyond, depending on the fiber transceiver used at each end.

  • @MrFoxRobert
    @MrFoxRobert22 күн бұрын

    👋👍

  • @tedharrison4109
    @tedharrison410922 күн бұрын

    Do you know if Tesla will be recycling the old and damaged batteries at this facility or will they send them overseas ?

  • @plywood76
    @plywood7622 күн бұрын

    Regarding your speculation about the different super computer roof area I doubt they are going to punch wholes through that roof for cooling equipment else why build separate structure for cooling towers. If anything the different roofing material is to guarantee extra long roof life with water resistance. Also I am surprised they just didn't build their own private nuclear power plant for this entire site infrastructure.

  • @GoCoyote

    @GoCoyote

    20 күн бұрын

    As to a nuclear power plant idea from an electrician in the power industry: The answer is location, time, and expense. Nuclear power is 2 to 4 times as expensive as solar and wind WITH battery backup (both of which Tesla already has a very cheap supply of). It also has very specific location requirements, which includes large supplies of cooling water as they are thermo-electric power plants. With an existing combined cycle power plant across the river, the chances of adequate cooling water being available for a nuke plant are slim to none. It is also near a major metropolitan area which creates a safety and security nightmare. Then there is time. Building a nuke plant will be a minimum of 20 years, and as long as 30, while the solar and battery systems went up in less than a year. Nuclear power has an EROI of 14 to 1, while new solar and wind range between 20 to 1 and 100 to 1, a much better return on energy investment (EROI is Energy Returned On energy Invested). So for nuclear one can get 14 kWhrs of energy back for every 1 kWhr of energy it took to build and operate the nuke plant, while wind and solar will get 20 to 100 kWhrs of energy from every 1 kWhr of energy it took to build and operate them. Adjusted for inflation, US taxpayers have spent an average of 3.5 billion dollars a year in direct subsidies on nuclear power since 1948, and just 0.35 billion (350 million) a year since 1990 on renewables, yet renewables are now usually the cheapest source of energy available. Nuclear energy is an economic dead end.

  • @The_DuMont_Network
    @The_DuMont_Network23 күн бұрын

    Hundreds of CTs, some hidden in the parking garage. More rolling out by the hour. Model Y production slowed if not stopped, very few in the lots. What is going on?

  • @TeslaElonSpaceXFan

    @TeslaElonSpaceXFan

    23 күн бұрын

    Model Y update/refresh/Juniper 😅

  • @ReinReads

    @ReinReads

    23 күн бұрын

    The new plan for the smaller vehicles is to use existing 3/Y line set ups. They are likely beginning to reconfigure to produce both refreshed (Juniper) Y and a smaller vehicle. Both are expected to come online Q4 or Q1’25.

  • @patrickspader4062

    @patrickspader4062

    23 күн бұрын

    @@ReinReadsIt’s not often that I read welll considered responses on Tesla forums but that was one of them. Yes let’s hope that this is the case and it’s not demand issues with Model Y and that the staff have been layed off because they are not required for the reconfiguration of the lines for the next cars.

  • @The_DuMont_Network

    @The_DuMont_Network

    23 күн бұрын

    I am concerned that I have not seen official announcement of this. The responses have certainly been appreciated and do make sense. IIRC, there are some Ys being made in Fremont? Last I saw there were tons stored at Taylor and possibly elsewhere. I'm still puzzled about all the CTs. It woukd seem they would want them delivered and reap the income, unless they are frontloading Q3?

  • @DessieDoolan

    @DessieDoolan

    23 күн бұрын

    FWIW. Joe's photos show no Cybertrucks visible in the parking garage. Might have been a one-off need to store them undercover a week ago.

  • @stevejones3875
    @stevejones387520 күн бұрын

    Is there a video today?

  • @JoeTegtmeyer

    @JoeTegtmeyer

    20 күн бұрын

    Yes

  • @VintageFilmChannel
    @VintageFilmChannel23 күн бұрын

    I would expect the the recycled battery cans might be used in the castings

  • @SoHoWarLord
    @SoHoWarLord23 күн бұрын

    Maybe a data center for all musk companies

  • @replica1052
    @replica105223 күн бұрын

    soldiers exist to protect civilians - there was never a moment in time when there were no soldiers

Келесі