The completion works at the Mochovce unit 3 site, were rather busy at the end of June 2018: Inside the reactor, a special bolt tensioner was brought in to seal the main dividing plane of the reactor. The tightener itself weighs 28 tonnes, but together with the test stand its weight climbed to an impressive 38 tonnes. It is used for sealing but also for unsealing the main flange joint of the reactor’s pressure vessel. This device can simultaneously and evenly tighten all the 60 bolts, attaining thereby a high degree of safety and required values of sealing. The sealed main containment level of the reactor is yet another step towards commissioning a nuclear power plant and enables further continuance of cold and hot hydrostatic tests.
Пікірлер: 13
Napriek snahe ekoteroristov a bláznivej Gréty má energia z jadra nezastupiteľný podiel na celkovej výrobe. Náhodné zdroje, ako vrtuľky či sklíčka na poliach a lúkach, tento podiel nenahradia.
@michaltruhlar3341
3 жыл бұрын
jen faktická: Zrovna ta Gréta jádro podporuje ;)
Dobrý deň, môžem sa spýtať, Rakúsko robí veľké halo, vraj sú tu vážne nedostatky a hrozí katastrofa, aká je pravda? + Obdivujem prácu robotníkov v elektrárni, skutočná poklona :)
@elektrarne
5 жыл бұрын
Na strašenie, ktoré robia rakúski protijadroví aktivisti, sme reagovali tu: www.seas.sk/clanok/protijadrovi-aktivisti-global2000-zamerne-siria-poplasne-spravy-o-mochovciach/380 a reagoval naň aj Úrad jadrového dozoru SR tu: www.ujd.gov.sk/ujd/www1.nsf/$All/036A67AA11D1BC43C12583D2004E0C11
@miyukiii5682
4 жыл бұрын
@@elektrarne Ďakujem :)
k comu to je dobre v porovnani s robotnikmi s momentovymi klucmi? setri cas montaze, resp. cas pracovnikov v blizkosti aktivnej zony?
@alexandertoth2808
Ай бұрын
utahovak nerobi s momentovym klucom, ale s pruznym natiahnutim svornikov pred dotiahnutim matky a potom uvolni svorniky, cim sa dosiahne spravny pritlak ... a ano ide aj o cas - urobi vsetky svorniky naraz
Výrobek Škoda JS
Pod zavesením bremenom chlapci? Loool rofl
@miroslavzmatlik9593
5 жыл бұрын
Ano aj pod zaveseným bremenom možno pracovať, podmienky takejto práce upravuje Z.z. 392/2006