Mammoet Mega Jack System in action by the Matagarup Bridge construction

Ғылым және технология

Watch how Mammoet successfully lifted both halves of the central arch of the new Matagarup Bridge, weighing 400t, using the innovative Mega Jack in Perth, Australia.
The team utilised the Mega Jack system where it was built as a construction tower 50m above one of the bridge piers and acted as a temporary support. The steel components of the arch measured 120m long x 35m wide were pulled using strand jacks, within a single day.
It was then held securely by the Mega Jack tower until the second wishbone was raised in the same manner and welded to create the complete central bridge arch.
For more information about Mammoet, please visit our website www.mammoet.com
#mammoet #amazingengineering #suspensionbridges #megajacksystem

Пікірлер: 10

  • @Dirk80241
    @Dirk802412 жыл бұрын

    Mammoet has a channel with high quality videos featuring good music and helpful explanations. Excellent work! Proud of this Dutch company!

  • @MammoetHeavyLifting

    @MammoetHeavyLifting

    2 жыл бұрын

    Thanks a lot 😊

  • @jimsvideos7201
    @jimsvideos72013 жыл бұрын

    Gorgeous bridge, but it was no doubt a challenge to understand the centers of gravity etc of all the pieces and how to manage them.

  • @chandrasekar7578
    @chandrasekar75783 жыл бұрын

    Mammoet morning from India!😊

  • @christianituze9007
    @christianituze90072 жыл бұрын

    Ah the fishbone project

  • @onnovanknotsenburg1177
    @onnovanknotsenburg11773 жыл бұрын

    I still think the biggest thing you move is time.

  • @Niidforseat

    @Niidforseat

    3 жыл бұрын

    And I think this was the best slogan they had.

  • @youme1414

    @youme1414

    3 жыл бұрын

    You can move time because time is not a thing.

  • @OmmerSyssel
    @OmmerSyssel2 жыл бұрын

    Please slow down texted explanations !!!!

  • @MammoetHeavyLifting

    @MammoetHeavyLifting

    2 жыл бұрын

    Thanks for your feedback!

Келесі