Lifting assembly to lift and tilt precast panel using four point lift

In this lecture, lifting assembly is created, its parts are explained, and tilting procedure of precast panel is explained.

Пікірлер: 14

  • @asjidmahmood7212
    @asjidmahmood72122 жыл бұрын

    Saud you have done great contribution to precast industry and structural & civil engineering I like and appreciate please continue to contribute your good work God bless you and give you good strength and health

  • @abdullahonline303
    @abdullahonline3033 жыл бұрын

    Informative and easy to understand. Well explained using technology and neat sketches.

  • @R-Flowerish
    @R-Flowerish2 жыл бұрын

    Excellent video and drawing!

  • @xohairehmed7726
    @xohairehmed77263 жыл бұрын

    Very informative and educational. More videos like this please.

  • @Innoxent2211
    @Innoxent221110 ай бұрын

    Just wanted to say that your video had some really good content. I learned a lot and gained some valuable knowledge from it. 👍 I do have a few questions though. I'm interested in learning more about the installation process from the very beginning. Could you provide some insights on the basics? Additionally, I'd love to know more about the drawings of erection, how they look, and how to study them in order to successfully implement them on the ground during installation.

  • @syedsaudahsan7888

    @syedsaudahsan7888

    10 ай бұрын

    Thanks for the compliments. For that you need the logistics plan, rigging plan, and then the method statement for the installation. its a big process. you need to ensure the safety parameters of each activity. Tell me your queries in detail so I'll try to make another tutorial on it in the future. Thanks

  • @YungItalianHandz
    @YungItalianHandz9 ай бұрын

    The whole point of the sheave is that it will equalise the force pulling on each end of the wire rope. Are you calculating different forces through opposite ends of the same wire rope going through the same sheave due to the sling angle being different on each side??? Or are you predicting the angle of the rope on each side of the sheave and therefore sheave position due to the force calculation? I hope you understand what I am trying to ask lol.

  • @ATAgroupo
    @ATAgroupo Жыл бұрын

    Thanks Sir

  • @syedsaudahsan7888

    @syedsaudahsan7888

    Жыл бұрын

    Welcome

  • @limukanidube9922
    @limukanidube9922 Жыл бұрын

    May you help with detail how you calculated the length of slings based on the weight of the load

  • @syedsaudahsan7888

    @syedsaudahsan7888

    Жыл бұрын

    calculate sling length based on 75 degree angle (at minimum). sling angle shall be measured with respect to the face of precast panel. Refer to precast concrete design handbook by PCI.

  • @vishaljoshi8667
    @vishaljoshi86673 жыл бұрын

    Hi I need help regarding foundation We need to lift foundation block There is no eye to put belt so we need to use some metal rod to kept in holo part of precast Is this rod need to certified if you have any specific standard for lifting rod kindly share

  • @syedsaudahsan7888

    @syedsaudahsan7888

    2 жыл бұрын

    you have make analysis first for rod. compute shear and tension forces based on placement of rod. using double shear force, dia of rod (mild steel) shall be calculated for specified factor of safety. third party certificate is also needed before use of any lifting item at site.

  • @Innoxent2211
    @Innoxent221110 ай бұрын

    Masha Allah great video...but i am going to join tomorrow insha Allah,but I don't have knowledge regarding bolts joints and hiw to install from the basic... kindly tell me the process of erection and standards sizes of elements It will be more helpful for me if you give me your email address or whatspp,so that uf i get any doubts on site inwould ask you... Jazakallahu Khair