Equalization Tank in Wastewater II Description and Design
Support this KZread channel and get access to design documents: www.patreon.com/user?u=83915893
This lecture is about the pre-treatment stage of flow equalization in a sewage treatment plant.
You will learn how an equalization tank functions and how to design it based on a simple rule of thumb and scientific approach.
Water treatment for beginners course: bit.ly/43vbJdF
Wastewater treatment for on-site projects course: bit.ly/44PkIHB
For business inquiries: wateracademia@gmail.com
Chapters:
0:00 Introduction
1:23 Process Description
4:42 Application
6:37 Components
7:22 Design Criteria
9:00 Step-by-Step Calculations
10:14 Solved Example
11:41 Scientific Approach
Other videos on this channel:
How to design a water softener: • How to calculate a sof...
Constructed Wetland for Wastewater Treatment: • Constructed Wetland fo...
How does MBBR work?: • How does MBBR work? Fu...
Design Calculations for MBBR Wastewater Treatment Plant: • Design Calculations fo...
Excel MBBR Wastewater Treatment Plant Design (xls): • Excel MBBR Wastewater ...
Difference between Chlorine Demand and Residual Chlorine: • Difference between Chl...
How to Remove Iron from Drinking Water: • How to Remove Iron fro...
How to Remove Nitrates from Well Water: • How to Remove Nitrates...
How to remove chlorine from water: • How to remove chlorine...
MCQ Water Treatment with Answers: • MCQ Water Treatment wi...
MCQ Wastewater Treatment with Answers: • Test your Knowledge: W...
Пікірлер: 12
Discount Coupon: Water treatment for beginners course: bit.ly/43vbJdF Discount Coupon: Wastewater treatment for on-site projects course: bit.ly/44PkIHB Complete MBBR spreadsheet calculations for only 4 USD: bit.ly/48FlAAJ
Your lecture is brief , sufficient and easy to learn. Thanks a lot 👍
@wateracademy5866
4 ай бұрын
You're welcome
Awesome lesson!!! I have a relatively simple residential aerobic surface spray disposal project that requires an uphill equalization tank to pump downhill too a dip then uphill then overall downhill to an ATU (equalization tank for uphill exist house to new downhill accessory house ATU). I’m definitely aerating eq tank now. I’ve never had to do that before. Now I know how to dose the downhill three chamber ATU. Thank you!! You’re a great teacher!!!
Amazing video thank you for sharing this information
@wateracademy5866
10 ай бұрын
So nice of you
Thank you for this amazing calculations ❤
@wateracademy5866
4 ай бұрын
You're welcome
Could you please reference what you used while designing? Your reply would be highly valuable for my research. thanks for this amazing video.
Can you please tell me the references about the values you are considering
En el tiempo 9:30 hay un error en la fórmula; se usa para hayar el volumen la fórmula d x H x W y debería ser d x L x W ya que H = d + borde libre (0.3 - 0.5 m).
@wateracademy5866
3 ай бұрын
For any reactor/tank, freeboard must be always added to the calculated volume